City of Lynnwood Project Update - 196th ST SW (SR 524) Improvement Project - July 15, 2022

Lynnwood Washington

196th St SW (SR 524) Improvement Project


Installing the foundation for a streetlight on the south side of 196th St SW between 44th Ave W and 40th Ave W

Installing the foundation for a streetlight on the south side of 196th St SW between 44th Ave W and 40th Ave W


Ongoing Planned Power Shutoffs

  • Ongoing planned electricity shutoffs
    • Crews are continuing to conduct planned power outages near the project corridor. These temporary power outages are needed to connect businesses, residences, and other properties to the newly upgraded electrical utilities near 196th St SW. This work will continue into August.
    • These temporary shutoffs are required for crews to safely complete this work. Some of this work may occur at night or early mornings.
    • Affected businesses and residents will be notified in advance with a doorhanger or letter. If you receive a doorhanger or letter and you have any questions about this work, please reach out to us.

We understand that the 196th St Improvement Project is impactful on the surrounding neighbors and traffic. Major roadway work for this project is expected to be finished in late 2023.

This schedule may change depending on weather conditions or availability of materials.

We thank you for your patience during construction. Our crews are working to complete upgrades as efficiently and effectively as possible. We will continue shifting travel lanes around work zones to allow us to maintain the safety of the crews and traveling public. 

Please follow all pedestrian and traffic control.


Weeks of July 11, 2022 and July 18, 2022

48th Ave W to 36th Ave W

  • Installing drainage, foundations, and retaining walls
  • Grading for sidewalks
  • Converting overhead utilities to underground
  • Digging (potholing) to confirm underground utility locations
  • Roadway excavation and paving

Other areas of work

  • Equipment and materials will be staged along 195th Pl SW for the duration of the project

Questions during construction? Contact us:

Email: 196street@LynnwoodWA.gov

Construction hotline: 425-224-2440

Webpage: www.LynnwoodWA.gov/196street


Title VI Non-Discrimination Information


For more information on this project, visit the project website and follow us on Twitter @LynnwoodStreets.