60th Ave W Sewer Repair Project


Side Sewer connection to manhole on 60th Ave W

Side Sewer connection to manhole on 60th Ave W


Traffic Impacts

Local access to businesses and residents will be maintained.

Please follow all traffic control signs.


December 10, 2021

  • Rodarte (the Contractor) has completed installation of the new sewer main for the project.
  • New sewer main has been installed on 204th ST SW, 60th Ave W and 202nd ST SW.
  • When the installation of the new sewer connection to Laurel Terrace Apts. on 60th Ave W all sewer work will be complete. This is anticipated to be completed next week.
  • Rodarte will be replacing curb & gutter, sidewalk and driveways early next week (Mon-Tues)
  • Pavement patching is planned for Wednesday. Motorists should expect delays primarily on 60th Ave while paving is taking place.

Questions during construction? Contact us:

Mike Whaley, Construction Manager, 425-670-5214, mwhaley@LynnwoodWA.gov