City of Lynnwood Project Update - 60th Ave W Sewer Repair - October 22, 2021

Lynnwood Washington

60th Ave W Sewer Repair Project


Installing new 8in. sewer pipe on 204th ST SW

Installing new 8in. sewer pipe on 204th ST SW


Traffic Impacts

Local access to businesses and residents will be maintained.

The detour around this project will be along 200th Ave, between Hwy 99 and 56th Ave W on the north and along 208th ST SW, between Hwy 99 and 56th Ave W on the south side.

Please follow all traffic control signs.


October 22, 2021

The contractor, Rodarte, will be:

  • Installing the new sewer main up 204th ST SW from the 60th Ave W intersection. This work will continue through next week. Weather dependent.
  • Current traffic control detours will remain in effect while crews are working on site and will be re-opened to two-way traffic at the end of each work day.

Questions during construction? Contact us:

Mike Whaley, Construction Manager, 425-670-5214, mwhaley@LynnwoodWA.gov

Webpage: www.LynnwoodWA.gov/60AveSewer


Title VI Non-Discrimination Information


For more information on this project, visit the project website and follow us on Twitter @LynnwoodStreets.