City of Lynnwood Project Update - South Lynnwood Park Renovation -October 12, 2021

Lynnwood Washington

South Lynnwood Park -

Renovation and Renewal Project

Accessible pathway to the shelter and boulder scramble at embankment slide have been installed.

Accessible pathway to the shelter and boulder scramble at embankment slide have been installed.


The entire park is fenced and closed during construction. The restroom and access to the Interurban trail are closed. 

On-street parking along the east side of 61st Ave West (adjacent to the park) is limited due to ongoing construction activities.


October 12, 2021 

Upcoming Work:

  • Form and pour concrete pathways
  • Install shotcrete seating logs at playground
  • Begin installing playground equipment
  • Begin soil preparation within planting areas

Project Contact:  Monica Thompson, PLA, CPSI - mthompson@LynnwoodWA.gov or 425-670-5567