City of Lynnwood Project Update - 60th Ave W Sewer Repair - October 7, 2021

Lynnwood Washington

60th Ave W Sewer Repair Project


60th Ave W Project Map

60th Ave W Project Map


Traffic Impacts

Traffic detours will be used as the main traffic control measure during construction to allow alternative access for heavy trucks.

Local access to businesses and residents will be maintained.

The detour around this project will be along 200th Ave, between Hwy 99 and 56th Ave W on the north and along 208th ST SW, between Hwy 99 and 56th Ave W on the south side.

Please follow all traffic control signs.


Project Information

Construction on the sewer main along 60th Ave W, 204th St SW and 202nd St SW will:

  • Replace 650 ft of deteriorating and sagging segments of concrete sewer main on 60th Ave W between 202nd St SW and 204th St SW.
  • Replace sewer laterals at Laurel Terrace Apartments, Cole Industrial and other lateral connections
  • Alleviate the reoccurring sewer backups at Laurel Terrace Apartments by installing a new manhole at the lateral connection
  • Replace 200 ft of deteriorating and sagging segment of sewer main on 202nd St SW West of 56th Ave W.
  • Replace 200 ft of deteriorating and sagging segment of sewer main on 204th St SW West of 60th Av W.

Project Schedule

This Project is scheduled from October  2021 to January 2022.


Questions during construction? Contact us:

Mike Whaley, Construction Manager, 425-670-5214, mwhaley@LynnwoodWA.gov

Webpage: www.LynnwoodWA.gov/60AveSewer


Title VI Non-Discrimination Information


For more information on this project, visit the project website and follow us on Twitter @LynnwoodStreets.