City of Lynnwood Project Update - South Lynnwood Park Renovation -August 17, 2021

Lynnwood Washington

South Lynnwood Park -

Renovation and Renewal Project

Urban soccer field curb, fence posts, and permeable aggregate base course has been installed.

Urban soccer field curb, fence posts, and permeable aggregate base course has been installed.


The entire park is fenced and closed during construction. The restroom and access to the Interurban trail are also closed. 

On-street parking along the east side of 61st Ave West (adjacent to the park) is limited due to ongoing construction activities.


August 17, 2021 

Upcoming Work:

  • Continue subsurface infrastructure: drainage and irrigation
  • Install foam pad and artificial turf at urban soccer field
  • Import subgrade fill for natural grass field
  • Prepare subgrade and base course for northern concrete and asphalt pathways
  • Prepare for boulder/rock walls

Project Contact:  Monica Thompson, PLA, CPSI - mthompson@LynnwoodWA.gov or 425-670-5567