City of Lynnwood Project Update - 196th ST SW (SR 524) Improvement Project - February 26, 2021

Lynnwood Washington

196th St SW (SR 524) Improvement Project


Removal of contaminated soil at 196th St SW and 44th Ave W.

Removal of contaminated soil at 196th St SW and 44th Ave W.


Traffic Impacts

As work progresses, please follow all pedestrian and traffic control.


Week of February 22, 2021

196th St SW and 44th Ave W (Precision Tune Quadrant)

  • Removal of contaminated soil 

Between 48th Ave W and 36th Ave W

  • Waterline placement at 48th Ave W
  • Clearing of surface materials and vegetation in front of Fred Meyer
  • Digging (potholing) to confirm underground utility locations 

Week of March 1, 2021

 196th St SW and 44th Ave W (Precision Tune Quadrant)

  • Removal of contaminated soil

Between 48th Ave W and 36th Ave W

  • Begin sewer line placement at 48th, heading east
  • Waterline placement at 48th Ave W
  • Digging (potholing) to confirm underground utility locations

Questions during construction? Contact us:

Email: 196street@LynnwoodWA.gov

Construction hotline: 425-224-2440

Webpage: www.LynnwoodWA.gov/196street

For more information on this project, visit the project website and follow us on Twitter @LynnwoodStreets.