Removal of contaminated soil at 196th St SW and 44th Ave W.
Traffic Impacts
As work progresses, please follow all pedestrian and traffic control.
Week of February 22, 2021
196th St SW and 44th Ave W (Precision Tune Quadrant)
- Removal of contaminated soil
Between 48th Ave W and 36th Ave W
- Waterline placement at 48th Ave W
- Clearing of surface materials and vegetation in front of Fred Meyer
- Digging (potholing) to confirm underground utility locations
Week of March 1, 2021
196th St SW and 44th Ave W (Precision Tune Quadrant)
- Removal of contaminated soil
Between 48th Ave W and 36th Ave W
- Begin sewer line placement at 48th, heading east
- Waterline placement at 48th Ave W
- Digging (potholing) to confirm underground utility locations
Questions during construction? Contact us:
Email: 196street@LynnwoodWA.gov
Construction hotline: 425-224-2440
Webpage: www.LynnwoodWA.gov/196street
For more information on this project, visit the project website and follow us on Twitter @LynnwoodStreets.
|