196th St SW (SR 524) Improvement Project


2021.02.12 Clearing and grubbing in front of Fred Meyer

Clearing of surface materials and vegetation in front of Fred Meyer on 196th St SW between 44th Ave W and 48th Ave W.


Traffic Impacts

As work progresses, please follow all pedestrian and traffic control.


Week of February 15, 2021 

196th St SW and 44th Ave W (formally Precision Tune Auto Care)

  • Removal of demolition debris
  • Traffic control for pedestrians

196th St SW between 48th Ave W and 36th Ave W

  • Clearing of surface materials and vegetation in front of Fred Meyer
  • Digging (potholing) in the street to confirm underground utility locations for waterline work at 48th Ave W

Week of February 22, 2021

196th St SW and 44th Ave W (formally Precision Tune Auto Care)

  • Removal of contaminated soil 

196th St SW (north side) between 48th Ave W and 36th Ave W

  • Clearing of surface materials and vegetation at 48th Ave W, moving east

Questions during construction? Contact us:

Email: 196street@LynnwoodWA.gov

Construction hotline: 425-224-2440

Webpage: www.LynnwoodWA.gov/196street

For more information on this project, visit the project website and follow us on Twitter @LynnwoodStreets.