City of Lynnwood Project Update - Lift Stations 4 & 8 - June 25, 2020

Lynnwood Washington

Lift Stations 4 & 8 Improvements


Backfilling the 24” PVC sewer pipe trench.

Backfilling the 24” PVC sewer pipe trench.


The Lift Station 4 in the Alderwood Mall parking lot near the movie theater is complete.

Work continues on the Lift Station 8 at the old bus barn location.


Week of June 22nd:

Lift Station 8:

The contractor has finished installing and backfilling the new 24” PVC sewer pipe. They  continue to bypass the existing gravity sewer system until all required tests associated with the installation are passed. Once complete, the contractor will transition to installing precast concrete wet wells and new lift station infrastructure.

Lift Station 4:

  • Completed

Please follow traffic control when crews are working.