 Stamped concrete splitter island at 172nd St Sw Roundabout
Traffic Impacts
- The east leg of 172nd St SW will be closed on March 30th, 2020 for construction of the roundabout.
- Only North and South bound traffic will be allowed at the intersection of 36th Ave W and 172nd St SW while the roundabout is constructed.
Local access will be maintained for residents within the closure. Please be aware of and follow the detour routes.
Please follow traffic control.
Week of May 11th
- Between 179th St SW and 165th Pl SW
- Form and place concrete for traffic islands
- Landscaping at the 172nd roundabout
- Place splitter island concrete at 172nd roundabout
- Grading the roundabout for truck apron concrete
- Landscape walls at the back of sidewalk to fit existing contours
- Raising utility lids to match new pavement
Week of May 18th
- Between 179th St SW and 165th Pl SW
- Form and place concrete for traffic islands
- Place truck apron concrete at the 172nd roundabout
- Place splitter island concrete at 172nd roundabout
- Landscape walls at the back of sidewalk to fit existing contours
- Placement of stamped concrete
- Raising utility lids to match new pavement
- Placing signs
- Placing monuments
Milestone Events:
- Activation of the signal at 179th, and opening of the roundabout is anticipated in June.