68th Ave W - CONSTRUCTION NOTICE
The contractor is scheduled to being construction on 68th Ave W between 196th ST SW and 204th ST SW on May 4th. Work will continue through an estimate of August 2020.
May 4th through estimated May 22nd
Contractors will begin by replacing the sidewalk ramps from 202nd to 198th ST SW for approximately 3 weeks.
Alternate pedestrian routes will be in place to allow for low impact to construction.
Next Phases
The paving operations of 68th Ave W will be performed in phases. Each phase will have a duration of approximately one week.
- NB Lane of 68th Ave W from 204th ST SW to 200th ST SW
- NB Lane of 68th Ave W from 200th ST SW to 196th ST SW
- SB Lane of 68th Ave W from 196th ST SW to 200th ST SW
- SB Lane of 68th Ave W from 200th ST SW to 204th ST SW
Detours will be in place to allow access to all residents and businesses, while work is being performed.
Paving dates are subject to weather and may change
For more information on this project visit the project website. And follow us on Twitter @LynnwoodStreets.
|