36th Avenue West Improvements


Paving 36th Ave W

Paving 36th Ave W


Traffic Impacts

  • The east leg of 172nd St SW will be closed on March 30th, 2020  for construction of the roundabout.
  • Only North and South bound traffic will be allowed at the intersection of 36th Ave W and 172nd St SW while the roundabout is constructed.

Local access will be maintained for residents within the closure.  Please be aware of and follow the detour routes.

Temporary channelization on 36th Ave W has moved the north and southbound lanes to the east side of the road. Please follow traffic control.


Week of April 20th

  • Between 179th St SW and 165th Pl SW
    • Form and place concrete for curbs at 172nd roundabout
    • Placing mast arms for the signal at 36th Ave W and 179th St SW
    • Paving 36th Ave W
    • Hydro seeding
    • Placing fences through project

Week of April 27th

  • Between 180th St SW and 165th Pl SW
    • Hot mix asphalt paving 36th Ave W
    • Working on Signal at 179th ST SW

Milestone Events:

  • Paving the final lift of asphalt from 180th Pl SW to 165th Pl SW will take place April 20th through May 1st.
  • Signal activation will take place the latter part of May or early June

For more information on this project, visit the project website and follow us on Twitter @LynnwoodStreets.