TRAFFIC & PEDESTRIAN IMPACTS:
- Expect temporary lane closures along 188th during construction. When road construction reaches an intersection a Uniformed Police Officer will safely direct vehicles and pedestrians through the intersection. Otherwise, for your safety, please follow all other instances of traffic control.
- During working hours, crosswalk ramps along 188th will be undergoing construction. During this time detour routes and flaggers will control all pedestrian crossing. During the weekend the crosswalk ramps along 188th will reopen, and the detour signage will be removed.
- Sidewalk routes through the construction zone are still open for pedestrian travel with compacted gravel replacing the concrete temporarily until the new ramps can be constructed. Pedestrian detours have also been set up in areas where demo work and concrete placement is in progress.
Last Week:
- Removal and replacement of the curb ramps, sidewalks and curb/gutter along 188th St SW between 48th Ave and 55th Ave West this week.
- The curb ramps at 55th Ave, 51st Place West, 52nd Ave and 48th Ave West have all been removed and will be replaced with ADA compliant ramps.
- Portions of the curb & gutter and sidewalks in those locations have also been removed and will be replaced to accommodate construction of the new ramps.
- Concrete work at these intersections are expected to continue into next week.
This Week:
Working hours during paving operations are from 7:00AM – 6:00PM, after hours two lanes of travel will remain open at all times.
For more information on this project visit the project website. And follow us on Twitter @LynnwoodStreets.
|