Construction
crews continue to make progress on the improvements to Meadowdale Playfields.
Multipurpose field 1 made final grade this week and is scheduled for the
E-layer installation next week 10/30 thru 11/3 . Multipurpose field 2 is not
far behind with work progressing on the concrete flatwork and fencing during
the first couple weeks of November. The turf crew is scheduled to start
installation on these fields in mid-November with completion in mid-December.
Softball fields
3,4,5 are on schedule with fencing and concrete flatwork progressing into
November. Crews will also work to complete underdrainage on field 3 and complete
top stone by mid-December.
Fencing,
landscaping and irrigation continue to progress as the turf is completed on
each field.
Although the
construction zone will be closed to the public several areas of the park will
remain open during construction including the northeast portion of the park and
several features including restrooms, playground, picnic area and portions of
the perimeter walkway.
For additional project information, visit the project page
at: http://www.lynnwoodwa.gov/City-Services/Engineering-Services/Public-Projects-and-Programs/City-Buildings-and-Facilities-Projects/Meadowdale-Playfields-Renovation.htm
|