Meadowdale
Playfields Renovation continues to move ahead as the contractor staff take advantage of
the nice weather. Crews have completed installation of the collector pipe and catch basins on multipurpose fields 1 and 2 . Work continues on importing base
course aggregate material to the multipurpose fields and will shift to the
softball fields as time allows.
The
Playfields have really started to take shape as fencing and concrete work has
now hit full speed, with work taking place an fields 1,2,3,4 and 5
simultaneously. During October expect to see work on landscaping, irrigation
and the asphalt pathway circling the fields. The project timeline has a
completion date of mid to late December.
Although
the construction zone will be closed to the public, several areas of the park
will remain open during construction. This includes the northeast portion of the
park, restrooms, playground, picnic area and
portions of the perimeter walkway.
For additional project information, visit the project page
at: http://www.lynnwoodwa.gov/City-Services/Engineering-Services/Public-Projects-and-Programs/City-Buildings-and-Facilities-Projects/Meadowdale-Playfields-Renovation.htm
|