Meadowdale Playfields Renovation


Meadowdale Playfields Renovation continues to move ahead as the contractor staff take advantage of the nice weather. Crews have completed installation of the collector pipe and catch basins on multipurpose fields 1 and 2 . Work continues on importing base course aggregate material to the multipurpose fields and will shift to the softball fields as time allows.

The Playfields have really started to take shape as fencing and concrete work has now hit full speed, with work taking place an fields 1,2,3,4 and 5 simultaneously. During October expect to see work on landscaping, irrigation and the asphalt pathway circling the fields. The project timeline has a completion date of mid to late December.

Although the construction zone will be closed to the public, several areas of the park will remain open during construction. This includes the northeast portion of the park, restrooms, playground, picnic area and portions of the perimeter walkway.

For additional project information, visit the project page at: http://www.lynnwoodwa.gov/City-Services/Engineering-Services/Public-Projects-and-Programs/City-Buildings-and-Facilities-Projects/Meadowdale-Playfields-Renovation.htm