City of Lynnwood Project Update - Lift Station and Force Main 16 July 6, 2016

Home Email Subscription RSS Facebook Twitter
Lynnwood Washington

Lift Station and Force Main 16 Project


LS16 7-6-16

Project will intercept flows that currently flow to Lift Station 10 which is near capacity. The Lift Station site is located just north of 196th Street SW on the west side of 56th Avenue W. The new force main will convey sewage from Lift Station 16 to an existing flow control structure just west of 68th Avenue W and 204th Street SW intersection.

Work this week included, from the week starting June 27th:

Force Main: The grind and overlay for the project is 91%.  56th Avenue, the road to the lift station, is the last road that will be ground and overlaid.  This will be scheduled after major construction activities for the lift station are complete.  

Lift Station: Last week’s activates were scheduled around the interior of the wet well, electrical infrastructure, and site improvements. 

Next week starting July 5th:

Lift Station:  The wet well mechanical installation will continue. The lift station mechanical and electrical interior rough-in will begin. 

For more information and to see pictures of this project visit the project website.