City of Lynnwood Project Update - Lift Station and Force Main 16 June 11, 2016

Home Email Subscription RSS Facebook Twitter
Lynnwood Washington

Lift Station and Force Main 16 Project


LS16 6-2-16

Project will intercept flows that currently flow to Lift Station 10 which is near capacity. The Lift Station site is located just north of 196th Street SW on the west side of 56th Avenue W. The new force main will convey sewage from Lift Station 16 to an existing flow control structure just west of 68th Avenue W and 204th Street SW intersection.

Work this week included, from the week starting June 06th:

Lift Station: Last week’s activates were scheduled around completing the roof, the interior of the wet well, and interior finishes.

Next week starting June 13th:

Lift Station:  The wet well interior will be constructed and equipment delivered.

For more information and to see pictures of this project visit the project website.