This project is expected to run from April 4th
through May 6th, 2016.
Last week, the contractor mobilized
on Monday, April 4th and commenced surveying. Work began on Tuesday
night, April 5th by “potholing” for unknown/unlocated utilities in
Alderwood Mall Parkway, primarily up toward the intersection of 184th
Street SW. Then they started the dry force main sewer installation at Lift
Station #4 on the East side of 182nd Street toward Alderwood Mall Parkway. Then they worked Southbound
in the center left turn lane working up the hill on to 182nd
St SW.
This week, installation continued with the dry force main
sewer, southbound in the center left turn lane from up the hill from 182nd
Street SW toward 184th Street SW intending to set the sewerage air release valve manhole.
Next week, installation is expected to continue
with the dry force main sewer, southbound in the center left turn lane from the
sewerage release valve manhole toward then end of the force main line just
south of 184th Street SW Monday and Tuesday nights. Asphalt prep and paving is expected to
occur on Wednesday and Thursday nights. Work will be occurring from 9:30pm until 6:00am
For more information and to see pictures of this project visit the project website.
|