Important update for on-land impact piledriving in Portage Bay

There is a horizontal green band that reads Rest of the West News. Above it is the letters W S D O T. An oval on the right reads state route 520.

In this update:


Important update for on-land impact piledriving: July 3, 2025

Hello neighbors,

Several weeks ago, we shared our plans to begin on-land impact piledriving by the Montlake Boulevard and SR 520 interchange between June 12 and July 3. Unfortunately, crews discovered an unknown underground utility conduit while installing piles and they had to temporarily stop their work for safety reasons.

To stay on schedule, we plan to install the three remaining on-land piles next week between Monday, July 7, to Friday, July 11. We will keep you informed through our email updates if we need to complete any additional on-land impact piledriving this summer.

What to expect

  • On-land impact piledriving
  • Work will happen Monday, July 7, through Friday, July 11
  • Work hours are from 8 a.m. to 5 p.m.

We know this isn’t ideal for neighbors. If you have any questions or concerns, please call us at 206-319-4520 or email us at sr520bridge@wsdot.wa.gov

What we’ve completed so far

Crew have installed 14 of the 17 piles we need to support our work trestle and the new temporary eastbound SR 520 off-ramp to Montlake Boulevard. We’ll install the last three piles in the same area we’ve been working (highlighted below in red).

Pile Driving Map with marker and red area circle

You may still hear or feel this work even if you're outside the red circle in the above map. If you have questions, call our hotline at 206-319-4520.

Don’t forget: Vibratory piledriving continues year-round

Throughout the summer, crews will continue installing piles in Portage Bay using a vibratory hammer. They'll drive piles as deep as possible and then return in Season 2 to finish the work using an impact hammer. 

Season 2 of in-water impact piledriving work begins September 1, 2025, and continues through April 30, 2026.


Construction Corner roundup

  • Ongoing: Bill Dawson Trail closed until 2030

Check out the SR 520 Construction Corner map for the most up-to-date information on closures and construction impacts


How to reach us and stay informed about SR 520 construction:

  • Call or text our project-specific construction hotlines with pressing questions or concerns related to the:
    • Montlake Project: 206-775-8885
    • SR 520/I-5 Connection Project: 206-316-2559 
    • Portage Bay Project: 206-319-4520
  • Call the SR 520 Program information line (206-200-9484, M-F 8 a.m. - 5 p.m.) with general SR 520 inquiries.
  • Email SR 520 staff with your questions about the project or construction activities.
  • Visit the SR 520 Construction Corner for the most up-to-date information on closures and construction impacts.
  • Visit the SR 520 Program website to find general information about the project.
  • Email Regina Glenn, WSDOT Megaprograms Diversity and Inclusion Manager, for more information about contracting opportunities.
  • Follow us on Twitter @wsdot_520 to get key news and updates about the SR 520 program.
  • View current Montlake Project construction photos, taken continuously day and night, by mounted construction cameras
  • Share the ROTW listserv with your friends and neighbors

If you have difficulty understanding English, you may request language assistance services free of charge by calling (360) 705-7090 or emailing TitleVI@WSDOT.WA.GOV.

Español - Spanish servicios de traducción Aviso a personas con dominio limitado del idioma inglés: Si usted tiene alguna dificultad en entender el idioma inglés, puede, sin costo alguno, solicitar asistencia lingüística con respecto a esta información llamando al (360) 705-7090, o envíe un mensaje de correo electrónico a: TitleVI@WSDOT.WA.GOV.

中文 - Chinese 翻译服务 如果您难以理解英文,则请致电:(360) 705-7090,或给我们发送电子邮件: TitleVI@WSDOT.WA.GOV,请求获取免费语言援助服务。

tiếng Việt-Vietnamese các dịch vụ dịch thuật Nếu quý vị không hiểu tiếng Anh, quý vị có thể yêu cầu dịch vụ trợ giúp ngôn ngữ, miễn phí, bằng cách gọi số (360) 705-7090 hoặc email cho chúng tôi tại: TitleVI@WSDOT.WA.GOV.

한국어 - Korean 번역 서비스 영어로 소통하는 것이 불편하시다면, (360) 705-7090으로 전화하시거나 다음 이메일로 연락하셔서 무료 언어 지원 서비스를 요청하실 수 있습니다: TitleVI@WSDOT.WA.GOV.

Af-soomaaliga - Somali Adeegyada Turjumaada Haddii ay kugu adag tahay inaad fahamtid Ingiriisida, waxaad, bilaash, ku codsan kartaa adeegyada caawimada luuqada adoo wacaaya (360) 705-7090 ama iimayl noogu soo dir: TitleVI@WSDOT.WA.GOV.

русский - Russian Услуги перевода Если вам трудно понимать английский язык, вы можете запросить бесплатные языковые услуги, позвонив по телефону (360) 705-7090 или написав нам на электронную почту: TitleVI@WSDOT.WA.GOV.

ِيَّة Arabic - اَلْعَ َرب خدمات الترجمة إذا كنت تجد صعوبة في فھم اللغة الإنجلیزیة، فیمكنك مجان ا طلب خدمات المساعدة اللغویة عن طریق الاتصال بالرقم .TitleVI@WSDOT.WA.GOV: الإلكتروني البرید عبر مراسلتنا أو)، 360) 705-7090

 


Thank you for signing up for the SR 520 Rest of the West news email updates. WSDOT will keep the community informed of current and planned construction activities through these updates and the tools listed above.