Weekly Hydro Ship Activity Report - February 19 through February 25, 2023

For the Week of February 19, 2023

NOAA OCS Logo

Weekly Hydro Ship Activity Report

Welcome to NOAA's Weekly Hydrographic Ship Activity Report! We hope you enjoy this reader-friendly layout for our weekly report as we update you on the progress of our NOAA-ship and contractor-run surveys. Please continue to direct your correspondences to progress.sketches@noaa.gov

Highlights of this edition

  • NOAA Ship Thomas Jefferson completed HSRR on TJ launch 2903

NOAA Ships

FERDINAND R. HASSLER

Recap
  • NOAA Ship Ferdinand R. Hassler has completed the processing of all their 2022 field season data, which has been submitted to the Atlantic Hydrographic Branch.  
  • NOAA Ship Ferdinand R. Hassler has concluded their field season and is alongside in New Castle, NH.
NOAA Ship Ferdinand R. Hassler, Photo courtesy of NOAA

Looking Forward

  • The ship is navigating through a few outstanding items associated with their winter repair package and looking forward to resuming operations in the Spring.

THOMAS JEFFERSON

Recap
  • NOAA Ship Thomas Jefferson completed HSRR on TJ launch 2903.
NOAA Ship Thomas Jefferson, Photo courtesy of NOAA

Looking Forward

  • Thomas Jefferson will be departing Norfolk, VA for Galveston, TX on 03MAR2023.

Fairweather

Recap:

  • NOAA Ship Fairweather has concluded their field season and is alongside MOC-P for dockside repairs.
NOAA Ship Fairweather, Photo courtesy of NOAA

Looking Forward

  • Fairweather will continue processing data acquired on project OPR-M328-FA-22 EXPRESS.

RAINIER 

Recap
  • NOAA Ship Rainier continued transiting to Honolulu, HI.
NOAA Ship Rainier, Photo courtesy of NOAA

Looking Forward

  • Rainier will conduct calibrations and sonar acceptance after arriving in Honolulu.

Contracted Vessels

Leidos_logo

 OPR-E347-KR-22 Central Chesapeake Bay, MD

Recap

  • Survey operations on the R/V Oyster Bay II were shut down on 19FEB2023 to process data to verify final coverage and identify any holidays requiring fill.

Looking Forward

  • Survey operations on the R/V Oyster Bay II will remain shut down until 05MAR2023 to process data to verify final coverage and identify any holidays requiring fill.
  • Data Processing ongoing in the Newport, RI Data Center and Field Office.