Weekly Hydro Ship Activity Report - February 5 through February 11, 2023
NOAA's National Ocean Service sent this bulletin at 02/14/2023 03:46 PM EST
For the Week of February 5, 2023
Weekly Hydro Ship Activity Report
Welcome to NOAA's Weekly Hydrographic Ship Activity Report! We hope you enjoy this reader-friendly layout for our weekly report as we update you on the progress of our NOAA-ship and contractor-run surveys. Please continue to direct your correspondences to progress.sketches@noaa.gov.
Highlights of this edition
Leidos continued survey operations on OPR-E347-KR-22 Central Chesapeake Bay, MD!
NOAA Ships
FERDINAND R. HASSLER
Recap
NOAA Ship Ferdinand R. Hassler has completed the processing of all their 2022 field season data, which has been submitted to the Atlantic Hydrographic Branch!
NOAA Ship Ferdinand R. Hassler has concluded their field season and is alongside in New Castle, NH.
Looking Forward
The ship is navigating through a few outstanding items associated with their winter repair package and looking forward to resuming operations in the Spring.
THOMAS JEFFERSON
Recap
The NOAA Ship Thomas Jefferson has concluded their field season and is alongside MOC-A!
The ship processed data acquired on projects OPR-W386-TJ-22 and OPR-W387-TJ-22, and submitted survey H13679.
The ship completed their first day of alongside ORT on 10FEB2023.
Looking Forward
Thomas Jefferson will continue processing data acquired on project OPR-W386-TJ-22 while working alongside MOC-A. The ship will complete alongside ORT on 17FEB2023, and continue preparation to get underway.
Fairweather
Recap:
NOAA Ship Fairweather has concluded their field season and is alongside MOC-P for dockside repairs!
Looking Forward
Fairweather will continue processing data acquired on project OPR-M328-FA-22 EXPRESS.
RAINIER
Recap
NOAA Ship Rainier has concluded their field season and is alongside in San Francisco!
Looking Forward
Rainier will be transiting from San Francisco to Honolulu, HI.
Contracted Vessels
OPR-E347-KR-22 Central Chesapeake Bay, MD
Recap
The R/V Oyster Bay II conducted survey operations on 07FEB2023 through 11FEB2023. Full or partial weather delays were encountered on 05FEB2023 and 06FEB2023.
Looking Forward
Survey operations on the R/V Oyster Bay II will continue as weather allows.
Data Processing ongoing in the Newport, RI Data Center and Field Office.