For the Week of November 27, 2022
![NOAA OCS Logo](https://content.govdelivery.com/attachments/fancy_images/USNOAANOS/2021/06/4635504/ocs-logo_original.jpg)
Weekly Hydro Ship Activity Report
Welcome to NOAA's Weekly Hydrographic Ship Activity Report! We hope you enjoy this reader-friendly layout for our weekly report as we update you on the progress of our NOAA-ship and contractor-run surveys. Please continue to direct your correspondences to progress.sketches@noaa.gov.
Highlights of this edition
- David Evans and Associates resumed survey operations on OPR-K356-KR-22 Approaches to Calcasieu, LA!
- Leidos resumed survey operations on OPR-E347-KR-22 Central Chesapeake Bay, MD!
NOAA Ships
FERDINAND R. HASSLER
Recap
- NOAA Ship Ferdinand R. Hassler has concluded their field season and is alongside in New Castle, NH.
|
|
|
![NOAA Ship Ferdinand R. Hassler, Photo courtesy of NOAA](https://content.govdelivery.com/attachments/fancy_images/USNOAANOS/2021/06/4651347/3609047/hassler_crop.jpg) |
- Scheduled repair period commences 17OCT2022 to 30NOV2022.
- Continue processing the remainder 2022 surveys.
THOMAS JEFFERSON
Recap
- The NOAA Ship Thomas Jefferson has concluded their field season and is alongside MOC-A!
- The Ship processed data acquired on projects OPR-W386-TJ-22 and OPR-W387-TJ-22.
- Dockside repair package commenced on 07NOV2022 and is ongoing until 23DEC2022.
|
|
|
![NOAA Ship Thomas Jefferson, Photo courtesy of NOAA](https://content.govdelivery.com/attachments/fancy_images/USNOAANOS/2021/06/4651348/3609048/tj_crop.jpg) |
-
Thomas Jefferson will continue processing data acquired on projects OPR-W386-TJ-22 and OPR-W387-TJ-22 while working alongside MOC-A.
Fairweather
Recap:
- NOAA Ship Fairweather has concluded their field season and is alongside MOC-P for dockside repairs!
|
|
|
![NOAA Ship Fairweather, Photo courtesy of NOAA](https://content.govdelivery.com/attachments/fancy_images/USNOAANOS/2021/06/4651349/3609049/fairweather_crop.jpg) |
-
Fairweather will continue processing data acquired on project OPR-M328-FA-22 EXPRESS.
RAINIER
Recap
- NOAA Ship Rainier has concluded their field season and is alongside in San Francisco!
|
|
|
![NOAA Ship Rainier, Photo courtesy of NOAA](https://content.govdelivery.com/attachments/fancy_images/USNOAANOS/2021/06/4651351/3609050/rainier_crop.jpg) |
Looking Forward
-
Rainier will be de-staging and getting the ship ready for the winter repair period in San Francisco.
Contracted Vessels
![DEA logo](https://content.govdelivery.com/attachments/fancy_images/USNOAANOS/2022/06/6002527/4170366/dea_crop.jpg) |
|
OPR-K356-KR-22 Approaches to Calcasieu, LA
|
Recap
- Project shut down for weather. Resumed survey operations on 03DEC2022.
- H13646 Fill and Investigations
- H13478 Crosslines
Looking Forward.
- H13478 Crosslines, Mainscheme, and investigations
- Bottom samples
- Complete project acquisition
- Blake transit to Gulfport, MS
- Project demobilization
![Leidos_logo](https://content.govdelivery.com/attachments/fancy_images/USNOAANOS/2021/07/4699836/leidos_original.png) |
|
OPR-E347-KR-22 Central Chesapeake Bay, MD |
Recap
- Resumed survey operations on the R/V Oyster Bay II on 28NOV2022.
- An equipment related delay occurred on 29NOV2022 and weather delays on 30NOV2022 and part of 01DEC2022.
Looking Forward
- The 30’ vessel R/V Oyster Bay II will continue survey operations.
- Data Processing ongoing in the Newport, RI Data Center and Field Office.
|