For the Week of October 30, 2022
![NOAA OCS Logo](https://content.govdelivery.com/attachments/fancy_images/USNOAANOS/2021/06/4635504/ocs-logo_original.jpg)
Weekly Hydro Ship Activity Report
Welcome to NOAA's Weekly Hydrographic Ship Activity Report! We hope you enjoy this reader-friendly layout for our weekly report as we update you on the progress of our NOAA-ship and contractor-run surveys. Please continue to direct your correspondences to progress.sketches@noaa.gov.
Highlights of this edition
- Leidos continued acquisition on OPR-E347-KR-22 Central Chesapeake Bay, MD!
- NOAA Ship Fairweather began multibeam acquisition on OPR-L397-FA-22 in the Channel Islands National Marine Sanctuary!
NOAA Ships
FERDINAND R. HASSLER
Recap
- NOAA Ship Ferdinand R. Hassler has concluded their field season and is alongside in New Castle, NH.
|
|
|
![NOAA Ship Ferdinand R. Hassler, Photo courtesy of NOAA](https://content.govdelivery.com/attachments/fancy_images/USNOAANOS/2021/06/4651347/3609047/hassler_crop.jpg) |
- Scheduled repair period commences 17OCT2022 to 30NOV2022.
- Continue processing the remainder 2022 surveys.
THOMAS JEFFERSON
Recap
- The NOAA Ship Thomas Jefferson processed data acquired on projects OPR-W386-TJ-22 and OPR-W387-TJ-22, while working alongside MOC-A for dockside repairs.
|
|
|
![NOAA Ship Thomas Jefferson, Photo courtesy of NOAA](https://content.govdelivery.com/attachments/fancy_images/USNOAANOS/2021/06/4651348/3609048/tj_crop.jpg) |
-
Thomas Jefferson will continue processing data acquired on projects OPR-W386-TJ-22 and OPR-W387-TJ-22 while working alongside MOC-A. Dockside repair package commences 07NOV2022 and is ongoing until 23DEC2022.
Fairweather
OPR-L397-FA-22 Channel Islands National Marine Sanctuary and OPR-M328-FA-22 EXPRESS
Recap:
- NOAA Ship Fairweather began multibeam acquisition on OPR-L397-FA-22 in the Channel Islands National Marine Sanctuary, opening sheets H13692 and H12556.
|
|
|
![NOAA Ship Fairweather, Photo courtesy of NOAA](https://content.govdelivery.com/attachments/fancy_images/USNOAANOS/2021/06/4651349/3609049/fairweather_crop.jpg) |
- NOAA Ship Fairweather will complete sheets H13692 and H12556 before heading into port to shelter from an incoming storm.
-
Fairweather will transit to the EXPRESS survey area on 08NOV2022 and begin acquisition shortly after.
RAINIER
Recap
- NOAA Ship Rainier has concluded their field season and is alongside in San Francisco.
|
|
|
![NOAA Ship Rainier, Photo courtesy of NOAA](https://content.govdelivery.com/attachments/fancy_images/USNOAANOS/2021/06/4651351/3609050/rainier_crop.jpg) |
Looking Forward
-
Rainier will be de-staging and getting the ship ready for the winter repair period in San Francisco.
Contracted Vessels
![DEA logo](https://content.govdelivery.com/attachments/fancy_images/USNOAANOS/2022/06/6002527/4170366/dea_crop.jpg) |
|
OPR-K356-KR-22 Approaches to Calcasieu, LA
|
Recap
- Project shut down for weather and project close out plan preparations. No weekly coverage to report.
Looking Forward
- Survey operations to resume on 06NOV2022
- Fill and Investigations (H13649, H13650, H13677, H13678)
- Continue H13678 MS
![Leidos_logo](https://content.govdelivery.com/attachments/fancy_images/USNOAANOS/2021/07/4699836/leidos_original.png) |
|
OPR-E347-KR-22 Central Chesapeake Bay, MD |
Recap
- The 30’ vessel R/V Oyster Bay II continued survey operations all week.
- The R/V Sea Innovator I was in port until 02NOV2022 processing data to verify quality and coverage from the main scheme data acquired to date.
- The R/V Sea Innovator I re-commenced survey operations on various sheets starting on 02NOV2022.
Looking Forward
|