Weekly Hydro Ship Activity Report - April 24 through April 30, 2022

For the Week of April 24, 2022

NOAA OCS Logo

Weekly Hydro Ship Activity Report

Welcome to NOAA's Weekly Hydrographic Ship Activity Report! We hope you enjoy this reader-friendly layout for our weekly report as we update you on the progress of our NOAA-ship and contractor-run surveys. Please continue to direct your correspondences to progress.sketches@noaa.gov

Highlights of this edition

  • NOAA Ship Thomas Jefferson completed transit to Cleveland, OH.
  • Geodynamics and eTrac prepared for their respective field season mobilization.

NOAA Ships

Ferdinand R. Hassler

OPR-J350-FH-22 Northern Gulf of Mexico

Recap
  • NOAA Ship Ferdinand R. Hassler continued acquisition on sheets H13620, H13621, H13622, H13625, H13626, and H13627 until 25APR2022 0535 UTC.
NOAA Ship Ferdinand R. Hassler, Photo courtesy of NOAA
  • Transited to Pascagoula, MS for port call to reinstall MVP and complete other maintenance work on the ship.

Looking Forward

  • NOAA Ship Ferdinand R. Hassler will be underway on 02MAY2022, and arrive at survey working grounds on 03MAY2022 to commenced 24-hr ship survey operations.

THOMAS JEFFERSON

OPR-W386-TJ-22 Approaches to Cleveland, OH 

Recap
  • NOAA Ship Thomas Jefferson completed their transit to Cleveland, OH where the crew had a well- deserved restful inport. 
NOAA Ship Thomas Jefferson, Photo courtesy of NOAA
Looking Forward
  • NOAA Ship Thomas Jefferson will be getting underway 02MAY2022 to begin surveying OPR-W386-TJ-22 and working on sheets H13616, H13607, and H13609.

FAIRWEATHER 

Recap
  • NOAA Ship Fairweather was alongside USCG Base Alameda finishing repairs to get underway and begin the season. AML Oceanographic and Vest Davit were aboard to install MVP-200 and to weight test the davits.
NOAA Ship Fairweather, Photo courtesy of NOAA

Looking Forward

  • NOAA Ship Fairweather will be getting underway 06MAY2022 pending repairs, to begin Operational Readiness Training followed by EM-712 trials.

RAINIER

OPR-T381-RA-22 Mariana Islands

Recap
  • NOAA Ship Rainier continued hydrographic and dive operations around Saipan, then headed south to Tinian Island and Aguijan Island.
NOAA Ship Rainier, Photo courtesy of NOAA
Looking Forward
  • NOAA Ship Rainier will inport next on 05MAY2022.

Contracted Vessels

Geodynamics LLC logo

 

OPR-Y396-KR-22 Western Lake Michigan, WI

Recap

  • Geodynamics prepared for project mobilization.
eTrac Logo

 

OPR-R320-KR-22 Cape Newenham, AK

Recap

  • R/V Norseman transited with the WAM-V stored on the deck from Homer, AK to Dillingham, AK.
  • R/V Thunder has been partially mobilized and is ready for barge transportation to Bethel, AK.

Looking Forward

  • Personnel will travel to Dillingham, AK.
  • R/V Norseman and the WAM-V will continue to be mobilized, calibrated and tested. Once the vessels are ready, R/V Norseman will transit to the survey site to begin Set Line Spacing data acquisition.
  • R/V Thunder will be put on a barge and transported to Bethel, AK.