UPDATE/LA - GIWW/DREDGING/SEC NOLA BNM 0776-25 UPDATE-3

united states coast guard

MARINERS ARE ADVISED BEGINNING JANUARY 08, 2026 AND CONTINUING UNTIL APPROXIMATELY JANUARY 23, 2026, THE HARVEY CANAL WILL BE CLOSED TO NAVIGATION AT THE HARVEY CANAL COMPLEX AT THE BASE OF THE LAPALCO BRIDGE ON THE GULF INTRACOASTAL WATERWAY (GIWW) AT POSITION 29- 52-13.33N, 90-04-07.36”W. THE CLOSURE IS DUE TO DREDGE OPERATIONS FOR THE SOUTHEAST LOUISIANA FLOOD PROTECTION AUTHORITY WEST AND WILL PERFORM ACTIVITY ON WEEKDAYS 07:00 A.M. TO 11:00 A.M. AND 01:00 P.M. TO 06:00 P.M. THERE WILL BE AN OPENING FROM 11:00 A.M. TO 01:00 P.M. TO ALLOW ANY VESSELS TO PASS. ALL VESSELS SHALL TRANSIT AT THEIR SLOWEST SAFE SPEED WHEN PASSING THE WORK SITE. THE ON-SCENE VESSEL M/V HUSTLER CAN BE CONTACTED ON VHF-FM- CHANNEL 13 FOR ADDITIONAL INFORMATION.
CANCEL AT//240000Z JAN 26//

BT