Gower Street - two way traffic from 21st May

May 2022

Air image

Final two - way traffic on Gower Street 

From the 21st May Gower Street will be two-way to traffic between Grafton Way and Euston Road.

This is the final section of Gower Street/Bloomsbury Street to change to two-way traffic.

Two-way roads update >>

Preparation works

In order to make the final change to two-way traffic on Gower Street we will be making the following changes:

Thursday 12th May – Friday 13th May: Minor repair works to Gower Street  (Euston Road slip road to Grafton Way).

Saturday 14th May – Sunday 14th May: Changing road markings on the Euston Road slip road outside UCLH and on Gower Street between Hampstead Road and Grafton Road. All westbound bus stops directly outside UCLH will be closed with Buses diverted down Gower Street and Grafton Way. 

Changing road markings on Tottenham Court Road between Warren Street and Euston Road. There will be a narrowed northbound lane during these works but the road will remain open at all times.

Saturday 21st May: Change to two-way traffic on Gower Street between Grafton Way and Euston Road. Adding new road makings on Tottenham Court Road outside Warren Street underground station. Work is expected to be completed by 1pm.

Upcoming works  >>


Advice for cyclists

The road layout will have changed so please:

  • take extra care
  • follow new signs
  • watch for pedestrians and drivers who may not yet be used to two-way traffic

Northbound cyclists on Gower Street are advised to use Grafton Way to access Euston or Hampstead Road. There is no cycle lane on the final northern section of Gower Street, but Grafton Way has a separate cycle lane and Tottenham Court Road has a bus and cycle only lane. There will be a new southbound cycle lane on Gower Street available for you to use.

TFL have quiet cycle routes listed on their website to explore these visit www.tfl.gov.uk/maps/cycle


Call us:

020 7974 4444

Email Us:

Westendproject@camden.gov.uk

Find out More:

Camden.gov.uk/westendproject

Look both ways

Please take care when crossing Gower Street and Bloomsbury Street and remember to

look both ways for traffic and cyclists

There are a number of pedestrian crossings along the road which we would encourage you to use, and we will have stewards on the street to remind people of the change for the first few days.


Advice for motorists

The road layout will have changed so please:

  • take extra care
  • follow new signs
  • watch for pedestrians and cyclists who may not yet be used to two-way traffic

We will have TfL staff on site to assist drivers for the first few days of the two way traffic. In particular please note the following changes:

1.  On Gower Street drivers will be able to travel in both directions between Grafton Way and Euston Road.

2. Drivers will no longer be able to turn left onto Euston Road from Tottenham Court Road – drivers should use Gower Street to access Euston Road westbound. 


Princes Circus transformation to start

Princes Circus

We are excited to share that work to transform Princes Circus into a beautiful new public space will begin on Monday 23rd May 2022. Idverde, who rejuvenated Whitfield Gardens and have just completed the stunning Alfred Place Gardens, will be once again working alongside us and our landscape designs LDA design. 

Work will start with the setting up of the site area and we hope to open the park to the public in early spring 2023. 

Princes Circus Programme  >>