Sunday Resurfacing works Grafton Way

November

2020

Grafton Way

Emergency drainage work on Grafton Way

We have unfortunately faced a minor delay on the resurfacing works following the emergency drainage work on Grafton Way. In order to finish the work as quickly and efficiently as possible we are going to be working on Sunday 22nd November and now finish on Tuesday 24th November.

Upcoming work  >>

Grafton Way - Sunday working

We apologise for the inconvenience caused as we will now be working on Sunday 22nd November. Working hours will be:

  • Mon - Fri: 8am – 5pm
  • Saturday: 8am – 1pm 
  • Sunday: 9am - 5pm

We now expect to be finished on Tuesday 24th November. We have updated the programme on the website where you can also find out detail on each of the road closures. 

Find out more >>


Call us:

0800 141 2543 24hr number

0207 974 4444 Camden Council

Email Us:

Westendproject@camden.gov.uk

Find out More:

Camden.gov.uk/westendproject

Grafton Way - road closures

The following roads will be closed as part of the emergency works:

  • Grafton Way between Huntley Street and Tottenham Court Road
  • Beaumont Place will be access from the east for ambulances only. Access off Tottenham Court Road will be maintained.

  • Grafton Way will be two-way to traffic in/out of the junction with Gower Street for local access only.

  • Huntley Street junction with Grafton Way will be access only for ambulances only between 8am - 6pm.