Resurfacing
We will start our resurfacing work on Monday 7th September and plan to have these works completed by the end of Tuesday 20th October.
Resurfacing High Holborn/Shaftesbury Avenue
- 7th September - 28th September
Resurfacing Bloomsbury Street
- 29th September – 8th October
Resurfacing New Oxford Street
- 9th October - 20th October
Road closures / access restrictions
There will be a number of road closures from Monday 7th September for full details refer to the resurfacing programme.
Monday 7th September - Wednesday 16th September
- No vehicle access at any time 24 hours a day to St Giles High Street.
- Access for residents and businesses only will be facilitated via Shaftesbury Avenue - Stacey Street - New Compton Street.
- No exit from Grape Street onto High Holborn. Grape Street will be access only from West Central Street. Vehicles should take extra care if reversing out.
- If you are within a closed area please leave rubbish on the nearest side street for collection.
- Pedestrian crossings on High Holborn, the northern end of Shaftesbury Avenue and across St Giles High Street will be closed – diversions will be in place.
|