Resurfacing
We will start our resurfacing on Monday 7th September and plan to have these works completed by the end of Tuesday 20th October.
Resurfacing High Holborn/Shaftesbury Avenue
- 17th September - 28th September
Resurfacing Bloomsbury Street
- 29th September – 8th October
Resurfacing New Oxford Street
- 9th October - 20th October
Noise and weekend working
To complete this work as quickly and efficiently as possible we will be working in sections and at weekends.
This resurfacing will require noisy work to break up the old road surface and involve large machinery moving around the area to lay the new surface.
Working hours will be:
- 8am - 6pm Mondays to Fridays
- 8am -1pm on Saturdays
- Please note not all weekends will include work.
Towards the end of the programme, later working hours on Saturdays as well as Sunday working may also be included. We will update the hours of work and any changes to dates on our website.
We apologise in advance for any inconvenience this will cause.
|