Works restarting 25th May
On the 30th March our contractors Eurovia paused all work on the West End Project in response to Coronavirus (COVID-19).
We expect to start a phased return to work towards the end of May, starting with small areas of work and building to a full return in mid-June.
|
|
|
Back to work dates
The dates below are indicative depending on continuing government guidance.
- 25th May – work to begin in Princes Circus at the junction of Bloomsbury Street and New Oxford Street for basement works
- 26th May – work to begin across the Princes Circus area for lighting connections
- 15th June – work to resume fully across the West End Project area
The pause to the project due to Coronavirus (COVID-19), will have caused delay to the overall programme and more information on this will be added to our website once the extent and impact are fully understood.
West End Project contact details
Call us:
Whitfield Garden: 0800 141 2543
Wider Project: 0845 3308 743
Email Us:
Westendproject@camden.gov.uk
Find out More:
Camden.gov.uk/westendproject
|
|
Eurovia will be following government guidance on physical distancing and working safely during this pandemic which includes:
- Using smaller working groups to allow for adequate physical distancing
- Creating extra space in the working area for parking to avoid the use of public transport
- Adding extra and / or larger welfare facilities for staff
- Using more road space / pavement space when working on areas to ensure physical distancing
Signage will be up across the site reminding you to remain 2 m from our work force as they continue this much needed transformational safety work.
|
|
|