Resurfacing around Holborn

January 2019

Resurfacing 2

Resurfacing the area around the Post Building

From Saturday 11th January we will be resurfacing the area around the Post Building including Museum Street, New Oxford Street and High Holborn. 

Resurfacing timetable >>

Resurfacing works

Between the 11th January and the 19th January we will be resurfacing the area around the the Post Building. We will work in sections to take up the existing road surface and lay a new surface. 

Letters to all businesses and residents are being delivered this week


Summary of work

We will be working between 8am and 6pm in the following locations:

  • Saturday 11th January – Resurfacing High Holborn north of Drury Lane and part of New Oxford Street between Museum Street and High Holborn.
  • Sunday 12th January – Resurfacing Museum Street and High Holborn
  • Saturday 18th January – Resurfacing New Oxford Street between Museum Street and High Holborn
  • Sunday 19th January – Resurfacing the junction of New Oxford Street, Museum Street and Bloomsbury Way

Noise and access

One of the noisiest parts of this work involves digging to prepare the road for resurfacing. We will also have large vehicles moving around the area to prepare and lay the new road surface.

We apologise for the inconvenience that this work will cause. We will be working as efficiently as possible to ensure that noise is kept to a minimum throughout.

Impacts

We will be working over the two weekends across the area. During this time we will need to put in place road closures, pedestrian diversions  and there will be closures to pedestrian crossings. 

For more detail on each section see our website for the programme. This timetable is subject to change and will be updated as the work continues.

Explore the resurfacing programme >>

Look both ways

Call us:

0845 3308 743 (24 hour)

Visit us:

Call us to make an appointment

Email Us:

Westendproject@camden.gov.uk

Find out More:

Camden.gov.uk/westendproject

camden.gov.uk