The garden design
Thank you again to everyone who took part in our engagement events last year and helped to shape the new designs. You can can find more information on what changes are taking place, including the layout plan, on our website.
Constructing the garden
The work to transform this much loved local space will start with some underground surveys and setting up barriers around the site.
To support this work we will need to close Tottenham Street from the 1st April to 30th May and suspend parking bays on Whitfield Street. Any changes to this programme will be updated on our website.
idverde working hours will be:
- Mon - Fri: 8am - 5pm
- As needed Saturday: 8am - 1pm
The noisiest work will be the cutting of new paving slabs and acoustic barriers will be put in place to reduce the sound.
Restoring the Fitzrovia Mural
Global Street Arts will be restoring the Fitzrovia Mural as part of our work in Whitfield Gardens. The render and paintwork needs to be stripped back and repainted as it is unstable.
The team at Global Street Arts have undertaken historical research in order to ensure that the repainted mural will be faithful to the original.
|
|
UCL entrance works
We will be laying new paving in the UCL entrance way on Gower Street from the 13th January for two weeks. Pedestrian access will be maintained at all times and UCL have arranged for no vehicle access during the construction period.
Call us:
Whitfield Garden: 0800 141 2543
Wider Project: 0845 3308 743 (24 hour)
Visit us:
Call us to make an appointment
Email Us:
Westendproject@camden.gov.uk
Find out More:
Camden.gov.uk/westendproject
|
|