West Cheltenham Transport Improvement Scheme road closures update - 30 April 2021

Having trouble viewing this email? View it as a Web page.

West Cheltenham Transport Improvement Scheme header

Scheme update and May road closures

30 April 2021

Upcoming road closures - May

Please forward this information on to people who may be interested. We hope these maps will help you plan your journeys through the area. 

We apologise in advance for any disruption caused. If you have any queries or questions please don't hesitate to get in touch via email - majorprojects@gloucestershire.gov.uk

Footway along A40 Gloucester Road is closed until 31 May - Closure of North side footway between Telstar Way and the Benhall Roundabout Bus Stop. Please see A40 Gloucester Road footway closure plan (PDF, 545.7 KB) for details of closure and diversion routes.

Map of the closure and diversion:

A40 footway closure and diversion

4 - 21 May: there will be a variety of closures on A40 Westbound lanes and Hatherley Lane overnight 7pm – 6am:

  • A40 (5 - 7 and 10 - 14 May): Westbound lanes from Arle Court roundabout to M5 Junction 11. This is a full closure and a diversion will be in place.
  • Hatherley Lane (4 - 5 and 17 - 21 May): Between Arle Court roundabout and B&Q roundabout. Access from B&Q roundabout to businesses maintained.

Please see A40 Westbound lanes and Hatherley Lane closures plan for details of closures and diversions. Map of the closure and diversion:

A40 closures May

Scheme update

Lots has been happening on site at the Arle Court roundabout end of the scheme. 

On the roundabout itself, surfacing works are complete to the main gyratory following night closures March/April, and the majority of new lining has been installed. 

Knights Brown contractor logos

At Hatherley Lane, the northbound works are largely complete and the final section at the compound entrance is being worked on at present. Southbound works have started with new kerbs being installed, moving into the centre island this week. Upcoming works here include surfacing and lighting.

On the A40 Westbound widening works have been completed. White lining is being carried out and traffic will be switched to a new alignment other than at Badgeworth Bridge this week to allow the new centre reserve to be completed. Works to Badgeworth Bridge are ongoing. 

On the A40 Eastbound works to Badgeworth Bridge are ongoing with centre reserve works coming up which include removal of the safety barrier.

On the B4063 arm, road widening works are complete other than final surfacing. Upcoming works here include footpath/cycleway upgrades. Cyclists will need to dismount for a short section while the existing footway/cycleway is upgraded. Look out for signs nearby. 

Subway works are progressing well. On the North Subway, the north east wall and pre-cast copings are complete with carriageway widening works underway. The copings are the decorative stone on the out side on the wall. The north west wall is also complete, with work on the copings ongoing. There is more to do on the safety barriers and footway/cycleway here. 

Please note the planned overnight closures above - we are steadily moving towards completing this section of the scheme and as always we are grateful for your ongoing patience. 

Arle Court roundabout, Cheltenham, from above

Further down towards Cheltenham, the retaining wall within GCHQ car park is 50 per cent complete.

Telstar Way junction improvements are under way, with site clearance complete in the central reserve and kerbing works progressing. Temporary traffic lights have been installed to allow works to continue on the new traffic signals installation which is 25 per cent complete.

GCHQ retaining wall

Retaining wall alongside A40

Between Telstar Way and Benhall roundabout, the temporary diversion of traffic into the central reservation is complete. Widening works to Benhall roundabout has started this week too. 

Traffic moved into temp central lane on A40 between Arle and Benhall

Traffic has been moved to the temporary lane in the central reservation


Highways England updates

B4634 Staverton bridge crossing the M5 between junctions 10 and 11

Most of the top deck hydro demolition and concrete repairs are now complete with two of the major and four of the minor phases complete. You can find more online here.

If you would like further information, please contact Highways England Customer Contact Centre on 0300 123 5000 open 24/7 or email: info@highwaysengland.co.uk

For information on all our works in the South West please follow us on Twitter @HighwaysSWEST


COVID-19 position

As Gloucestershire moves between different levels of Coronavirus restrictions, we want to reassure you that we are working with our highways contractors in Gloucestershire to protect all staff, following updated government and industry guidance regarding COVID-19 and construction work. 

We will continue to make progress with the West Cheltenham Transport Improvement Scheme using the principles of social distancing, bubbles and working remotely. 


Get others involved

As always please do send this message on to anyone who you think would be interested in these important improvements in Cheltenham. Anyone can sign up to receive future news bulletins about this scheme too.