West Cheltenham Transport Improvement Scheme update - 7 August 2020

Having trouble viewing this email? View it as a Web page.

West Cheltenham Transport Improvement Scheme header

Scheme update - road closures

7 August 2020


B4063 closure

The B4063 arm of Arle Court roundabout will be closed for five nights, 10 - 14 August over night between 8pm and 6am. This is so crews can continue to divert utilities and remove the island here.

A signed diversion will be in place.

Arle Court round about lane closures

Arle Court roundabout will be down to one lane overnight on 10 August so crews can work safely on site. 

Please remember there is a speed limit of 40mph on the Golden Valley Bypass at the moment. This is to keep crews safe who are working in the central reservation.

We apologise for any inconvenience caused. Please contact the site team if you have any concerns:

  • Cath Waller - 07818 432183 
  • Richard Knight - 07833 553418

Map of the closures:

B4063  at Arle Court roundabout is closed over night 10 - 14 August 2020

Knight Brown considerate contractor logo

Construction update from Knights Brown

Firstly we would like to thank you all for your patience and the warm welcome we have received over the last month while we have been setting up our site and starting prep work for the project. It has been a busy and positive start to the project even with the added challenges that Covid-19 has brought us all. We would like to reassure you that our works are being delivered in line with Covid-19 government guidelines.

Over the past month we have completed a number of key preparatory tasks which will pave the way for the future work that is to be completed. Our site offices and compound have now been installed and will be our base for the duration of the scheme.

We have begun to install traffic management measures which will enable us to keep you and our workforce safe throughout the project. To complete the works we have also had to close the subway under the A40 by Arle Court roundabout. Please follow the designated diversion route as it has been put in place to keep you safe.

We will also be putting in place a temporary bus stop on the A40 east bound from the 27 June. The new bus stop will be situated approximately 100m east of the original bus stop.

Other key areas of work that have been completed include:

  • service and utility diversions (gas, electricity, broadband)
  • site clearance works on the B4063
  • demolition of the existing footbridge Fiddlers Green Lane to the A40
  • drainage works on Arle Court Roundabout
  • prep work for the piling works required for the road widening and subway works on the A40.

We have also completed night works at Hatherley Lane and on the A40 over the last week. These works enabled us to remove the splitter island and install a cable crossing across the road at Hatherley Lane and install traffic barriers and narrow lanes as part of our traffic management measures on the A40.

Fiddlers Green Lane footbridge is demolished

The footbridge at Fiddlers Green Lane is demolished

Looking ahead

Over the next month work will be completed or continue in the following areas:

  • Arle Court Roundabout—drainage work will continue
  • North East Subway – piling works, drainage and wall foundations will begin
  • Hatherley Lane – Service diversions and excavation work will begin for the new road construction
  • B4063 – Footpath diversions, service and utility diversions and road excavation works
  • A40 – Excavation and new road construction

If you have any questions or queries in relation to the information provided or on the scheme in general please get in contact with us at WCTIS@knightsbrown.co.uk or on 07818 432183.

Digging up centre of Hatherley Road in Cheltenham

Working on Hatherley Lane central reservation


COVID-19 position

We want to reassure you that we are working with our highways contractors in Gloucestershire to protect all staff, following government and industry guidance regarding COVID-19 and construction work.

We are making progress with the West Cheltenham Transport Improvement Scheme using the principles of social distancing and working remotely.


Get others involved

As always please do send this message on to anyone who you think would be interested in these important improvements in Cheltenham. Anyone can sign up to receive future news bulletins about this scheme too.