Chapel Foundry Culvert Replacement - Update 7

Having trouble viewing this email? View it as a Web page.

Banner Lower Text

29/10/2019

Update 7 

Sheffield Road Reopened & Phase 3 Culvert Installation 

 

Installation of New Culvert Units - Phase 3

Works this month have been focussed on the installation of Phase 3 of the new culvert and installing the piled wall to enable the final stage of the scheme to be undertaken. The Culvert units for Phase 3 were installed on Monday 21st October and the waterproofing & backfilling of the units began the following day.

Update 7 Culvert Install

Completion of phase 3 meant that it was possible to remove the traffic lights on Sheffield Road on Monday 28th October following a short closure on the previous day to allow the road resurfacing to take place.

Road markings will be laid as soon as possible but it should not be necessary to close the road in order for this to take place.

We would like to thank everyone for their patience while the vital work to replace the culvert took place.

Update 7 Resurfacing

Phase 4 Culvert Replacement and Scheme Completion Works

The final stage of the scheme (Phase 4 culvert installation and all finishing works i.e. walling, fencing & resurfacing) will be undertaken from within the Derbyshire County Council Depot. 


Next Update:

A scheme update will be issued fortnightly and at key stages throughout the project - any queries in the interim period can be made to the Highways Hub on Highways.hub@derbyshire.gov.uk

Previous Scheme Information sheets can be found via the Chapel Foundry Culvert Web Page at Chapel Foundry Culvert Updates