  Loop 1604 North Expansion Project
Closure Notice
Four new ramps opening this weekend on Loop 1604
New ramps provide easier and safer access for drivers
TxDOT is opening four new ramps on Loop 1604 this weekend at Hausman Rd., Babcock Rd., Vance Jackson Rd. and Lockhill Selma Rd. The new ramps will provide easier and safer access for drivers as they travel the corridor in north Bexar County.
The ramp openings will take place on the weekend of May 2, 2025. Details on each ramp opening are listed below.
Morning of Friday, May 2
- The new westbound exit ramp to Lockhill Selma Rd. will open. The existing exit ramp will permanently close.
- The new eastbound entrance ramp from Vance Jackson Rd. will open. The existing entrance ramp from Lockhill Selma Rd. will close.
On or before 5 a.m. Monday, May 5
- The new entrance ramp from Hausman Rd. will open.
- The new exit ramp to Babcock Rd. will open.
- The existing entrance ramp from Kyle Seale Parkway will close.
TxDOT is committed to scheduling construction that creates the least impact to traffic and allows work to be completed safely. Drivers are encouraged to consider the construction schedule as they plan commutes and keep this important information in mind:
- Construction schedules are weather permitting and subject to change.
- Access to businesses will remain open during construction.
- Closures may open early if work is complete and conditions are safe for drivers.
- Subscribe for project updates and closure information at Loop1604North.com.
- Visit DriveTexas.org for the latest information on closures and road conditions.
Background
The Loop 1604 North Expansion is a Texas Clear Lanes project aimed at enhancing safety, improving mobility and reducing congestion along 23 miles of Loop 1604 from SH 16 (Bandera Rd.) to I-35. This $1.4 billion project includes the expansion of mainlanes from a 4- to 10-lane expressway, high-occupancy vehicles (HOV) lanes in each direction, a multi-level interchange at I-10, an innovative intersection at Blanco Road, and bicycle and pedestrian accommodations on the frontage roads.
The expansion is planned in six segments with five segments currently under construction.
- Segment 1, from SH 16 to I-10, is on schedule to be complete in 2025.
- Segment 2, the Loop 1604 and I-10 interchange, is on schedule to be complete by 2027. The first flyover ramp opened December 2024 and a second ramp is on schedule to open early summer 2025.
- Segment 3, from I-10 to US 281, is on schedule to be complete by early 2026.
- Segment 4, from US 281 to Redland Road, is on schedule to be complete by 2027.
- Segment 5, from Redland Road to Judson Road, began construction spring 2025.
|