I-35 from FM 3009 to FM 1518
Northbound
- Sunday, December 15, until Friday, December 20, 9 p.m. to 5 a.m. Multiple mainlane closures (3) of northbound I-35, exit ramp, and entrance ramp from Evans Road to Roy Richard Drive (FM 3009) for barrier work. Traffic should use next available ramps.
Southbound
- Through Saturday, December 21, long-term closure (24/7). Right lane closure on the southbound frontage road of I-35 from FM 3009 to Schertz Parkway for roadway work.
- Sunday, December 15, until Saturday, December 21, 9 p.m. to 5 a.m. Multiple mainlane closures (3), and entrance ramp closure, and exit ramp closure of southbound I-35 from Roy Richard Drive to Schertz Parkway for column and cap work. Traffic should use next entrance and exit ramps.
- Sunday, December 15, until Saturday, December 21, 9 p.m. to 5 a.m. Full closure of southbound I-35 frontage road and exit ramp from Schertz Parkway to Corporate Drive for drilled shaft, column, and cap work. Traffic should follow detour signs.
- Sunday, December 15, until Saturday, December 21, 9 p.m. to 5 a.m. Multiple mainlane closures (3) of southbound I-35 from Schertz Parkway to Forum Parkway for bridge structure work.
I-35 from FM 1518 to Loop 1604
Northbound
- Through Saturday, August 2, 2025, long-term closure (24/7). Left lane closure on northbound frontage road of I-35 from Forum Parkway to Forum Access Road for construction work.
- Through Sunday, December 22, long-term closure (24/7). Right lane closure on northbound exit ramp and left lane closure on northbound frontage road from Forum Access Road to Olympia Parkway for construction work.
- Through Monday, May 5, 2025, long-term closure (24/7). Exit ramp closure on northbound I-35 to Evans Road for construction work.
- Sunday, December 15, 9 p.m. to 5 a.m. Full closure of northbound frontage on I-35 from Olympia Parkway to Pasatiempo for construction work. Traffic can follow the detour signs.
- Sunday, December 15, until Tuesday, December 17, 9 p.m. to 5 a.m. Full closure of westbound Loop 1604 frontage road at Agora Parkway to northbound I-35 frontage road at Forum Access Road and full closure of northbound I-35 collector ramp for bridge column and cap work. Traffic should follow detour signs.
- Sunday, December 15, until Thursday, December 19, 9 p.m. to 5 a.m. Multiple lane closures (3) of northbound I-35 mainlanes, exit ramp, and entrance ramp from Forum Parkway to Evans Road for bridge column and cap work. Traffic should use next exit and entrance ramps.
- Sunday, December 15, until Tuesday, December 17, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road from Forum Parkway to Forum Access Road for bridge cap and column work. Traffic should follow detour signs.
- Sunday, December 15, until Saturday, December 21, 9 p.m. to 5 a.m. Full closure of northbound I-35 collector ramp at Loop 1604 interchange, northbound I-35 frontage road at Pat Booker Road, and westbound Loop 1604 frontage road at Agora Parkway to northbound I-35 frontage road at Forum Parkway for bridge column and cap work. Traffic follows detour signs.
- Monday, December 16, until Saturday, December 21, 9 p.m. to 7 a.m. Full closure of westbound Loop 1604 frontage road at Agora Parkway to northbound I-35 frontage road at Olympia Parkway for bridge column and cap work. Traffic should follow detour signs.
- Monday, December 16, until Wednesday, December 18, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road and exit ramp from Forum Parkway to Olympia Parkway for column cap work. Traffic should follow detour signs.
- Tuesday, December 17, until Saturday, December 21, 9 p.m. to 7 a.m. Alternating lane closures of northbound I-35 frontage road from Olympia Parkway to Pasatiempo for bridge beam setting.
- Tuesday, December 17, until Saturday, December 21, 9 p.m. to 7 a.m. Multiple mainlane closures (3) on northbound I-35 from Olympia Parkway to Evans Road for bridge beam setting.
Southbound
- Through Sunday, May 25, 2025, long-term closure (24/7). Left lane closure on southbound frontage road of I-35 from Forum Parkway to Old Austin Road for bridge and roadway work.
- Through Sunday, May 25, 2025, long-term closure (24/7). Right lane closure on I-35 southbound to Loop 1604 westbound connector ramp for construction work.
- Sunday, December 15, until Tuesday, December 17, 9 p.m. to 5 a.m. Full closure of southbound I-35 frontage road from Retama Parkway to Olympia Parkway for bridge column work. Traffic should follow detour signs.
- Sunday, December 15, until Tuesday, December 17, 9 p.m. to 5 a.m. Full closure of southbound I-35 frontage road from Old Austin Road to Forum Parkway for bridge deck work. Traffic should follow detour signs.
- Sunday, December 15, until Tuesday, December 17, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road from Old Austin Road to Forum Parkway and full closure of northbound I-35 Olympia Parkway exit ramp for pavement, column, and cap work. Traffic should follow detour signs.
- Sunday, December 15, until Thursday, December 19, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road, exit ramp from Evans Road to Arcadia Drive, full closure of northbound to southbound turnaround at Evans Road at I-35 intersection and full closure on the westbound lanes on Evans Road at I-35 intersection for bridge column and cap work. Traffic should follow detour signs.
- Sunday, December 15, until Tuesday, December 17, 9 p.m. to 5 a.m. Full closure of southbound I-35 frontage road and entrance ramp from Olympia Parkway to Forum Parkway for bridge deck work. Traffic should follow detour signs.
- Sunday, December 15, until Saturday, December 21, 9 p.m. to 5 a.m. Full closure of southbound I-35 frontage road from Corporate Drive to Evans Road and full closure of eastbound and westbound lanes of Evans Road at I-35 intersection for bridge column and cap work. Traffic should follow detour signs.
- Sunday, December 15, until Wednesday, December 18, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road from Forum Parkway to Gateway Boulevard for striping, barrier, temporary pavement, and demolition works. Traffic should follow detour signs.
- Sunday, December 15, until Tuesday, December 17, 9 p.m. to 5 a.m. Multiple mainlane closures (3) of southbound I-35 from Forum Parkway to Ferrell Road for bridge structure, striping and barrier work.
- Monday, December 16, until Thursday, December 19, 9 a.m. to 3 p.m. Left lane closure of southbound I-35 frontage road from Retama Parkway to Olympia Parkway for traffic signal equipment installation work.
- Monday, December 16, until Saturday, December 21, 9 p.m. to 5 a.m. Multiple mainlane closures (3) on southbound I-35 from Forum Parkway to McMorris Boulevard for bridge column and cap work.
- Monday, December 16, until Thursday, December 19, 9 p.m. to 5 a.m. Multiple lane closures (3) on southbound I-35 main lanes from Corporate Drive to Evans Road for precast cap setting.
- Monday, December 16, until Thursday, December 19, 9 p.m. to 5 a.m. Full closure on southbound frontage road of I-35 from Corporate Drive to Evans Road and full closure of eastbound and westbound lanes of Evans Road for precast cap setting. Traffic should follow detour signs.
I-35 and Loop 1604 Interchange
Northbound
- Sunday, December 15, until Saturday, December 21, 9 p.m. to 5 a.m. Full closure on westbound I-35 collector ramp and northbound I-35 to westbound Loop 1604 connector ramp, full closure on southbound I-35 to westbound Loop 1604 connector ramp, full closure on eastbound frontage road from entrance ramp to IKEA-RBFCU Parkway and full closure of northbound and southbound lanes of IKEA-RBFCU Parkway at Loop 1604, exit ramp closure to Olympia Parkway for deck, overhangs, column work.
- Sunday, December 15, until Tuesday, December 17, 9 p.m. to 5 a.m. Full closure of northbound I-35 collector ramp at the Loop 1604 interchange for striping, barrier, and construction entrance work. Traffic should follow detour signs.
- Monday, December 16, until Thursday, December 19, 9 p.m. to 5 a.m. Full closure of northbound I-35 collector ramp at the Loop 1604 interchange for column cap setting. Traffic should follow detour signs.
- Monday, December 16, until Thursday, December 19, 9 p.m. to 5 a.m. Full closure of northbound I-35 connector ramp to westbound Loop 1604 mainlanes for column cap setting. Traffic should follow detour signs.
- Monday, December 16, until Wednesday, December 18, 9 p.m. to 5 a.m. Full closure of northbound I-35 collector ramp at the Loop 1604 interchange for drilled shaft work. Traffic should follow detour signs.
- Monday, December 16, until Wednesday, December 18, 9 p.m. to 5 a.m. Full closure of westbound I-35 collector ramp at the Loop 1604 interchange, full closure of northbound I-35 connector ramp to westbound Loop 1604 mainlanes, full closure of southbound I-35 connector ramp to westbound Loop 1604 mainlanes, and full closure of northbound and southbound lanes of IKEA-RBFCU Parkway at Loop 1604 intersection for bridge column and cap work. Traffic should follow detour signs.
- Wednesday, December 18, until Friday, December 20, 9 p.m. to 5 a.m. Full closure of westbound Loop 1604 collector ramp at I-35 interchange, northbound I-35 connector ramp to westbound Loop 1604 mainlanes, and southbound I-35 collector ramp at Loop 1604 interchange for bridge deck work. Traffic should follow detour signs.
Southbound
- Sunday, December 15, until Saturday, December 21, 9 p.m. to 5 a.m. Full closure of southbound I-35 frontage road from Arcadia Drive to Olympia Parkway, westbound Loop 1604 collector ramp at I-35 interchange, northbound I-35 connector ramp to westbound Loop 1604 mainlanes, southbound I-35 connector ramp to westbound Loop 1604 mainlanes, eastbound Loop 1604 frontage road from IKEA-RBFCU Parkway exit ramp to IKEA-RBFCU Parkway and northbound and southbound lanes of IKEA-RBFCU Parkway at Loop 1604 for bridge column, cap and deck work. Traffic should follow detour signs.
- Sunday, December 15, 9 p.m. to 5 a.m. Full closure of westbound Loop 1604 mainlanes from Pat Booker Road to Gateway Boulevard, full closure of southbound I-35 collector ramp at Loop 1604 interchange for bridge deck work. Traffic should follow detour signs.
- Sunday, December 15, until Saturday, December 21, 9 p.m. to 5 a.m. Full closure of southbound I-35 collector ramp at Loop 1604 interchange for bridge deck work. Traffic should follow detour signs.
- Sunday, December 15, until Friday, December 20, 9 p.m. to 5 a.m. Full closure of eastbound Loop 1604 connector ramp to southbound I-35 mainlanes for bridge deck work. Traffic should follow detour signs.
- Sunday, December 15, until Wednesday, December 18, 9 p.m. to 5 a.m. Full closure of southbound I-35 frontage road from IKEA-RBFCU Parkway to Pat Booker Road, eastbound Loop 1604 connector ramp to southbound I-35 mainlanes, and southbound I-35 collector ramp closure at Loop 1604 interchange for wall demolition, bridge column, and cap work. Traffic should follow detour signs.
- Sunday, December 15, until Wednesday, December 18, 9 p.m. to 5 a.m. Southbound I-35 to westbound Loop 1604 connector ramp closure and alternating lane closures on southbound mainlanes of I-35 at the exit to Loop 1604 for column and cap work. Traffic should follow detour signs.
- Monday, December 16, until Wednesday, December 18, 9 p.m. to 5 a.m. Full closure of eastbound Loop 1604 collector ramp at the I-35 interchange and full closure of southbound I-35 connector ramp to eastbound Loop 1604 mainlanes for barrier work. Traffic should follow detour signs.
- Monday, December 16, until Wednesday, December 18, 9 p.m. to 5 a.m. Full closure of southbound I-35 frontage road from IKEA-RBFCU Parkway to Pat Booker Road, eastbound Loop 1604 connector ramp to southbound I-35 mainlanes, and southbound I-35 collector ramp at the Loop 1604 interchange for striping and barrier work. Traffic should follow detour signs.
- Monday, December 16, until Thursday, December 19, 9 p.m. to 5 a.m. Full closure of westbound Loop 1604 connector ramp to southbound I-35 mainlanes for pavement work. Traffic should follow detour signs.
- Monday, December 16, until Wednesday, December 18, 9 p.m. to 5 a.m. Full closure of southbound I-35 collector ramp and southbound to westbound connector ramp at Loop 1604 interchange for bridge deck work. Traffic should follow detour signs.
- Tuesday, December 17, until Thursday, December 19, 9 p.m. to 5 a.m. Full closure of eastbound Loop 1604 collector ramp at I-35 interchange and southbound I-35 collector ramp at Loop 1604 interchange for bridge deck work. Traffic should follow detour signs.
Loop 1604 from I-35 Interchange to Nacogdoches Road
Eastbound
- Through Monday, March 31, 2025, long-term closure (24/7). Left lane closure on eastbound frontage road of Loop 1604 from Lookout Road to IKEA-RBFCU Boulevard for construction.
- Sunday, December 15, until Saturday, December 21, 9 p.m. to 7 a.m. Full closure of eastbound Loop 1604 collector ramps at I-35 interchange and full closure of eastbound Loop 1604 entrance ramp from Lookout Road to IKEA-RBFCU Parkway for bridge column and cap work. Traffic should follow detour signs.
- Monday, December 16, until Thursday, December 19, 9 p.m. to 5 a.m. Full closure of eastbound Loop 1604 mainlanes from Lookout Road to Pat Booker Road for bridge deck work. Traffic should follow detour signs.
- Monday, December 16, until Wednesday, December 18, 9 p.m. to 5 a.m. Alternating lane closures of eastbound Loop 1604 mainlanes from Nacogdoches Road to Pat Booker Road for bridge column work.
- Monday, December 16, until Thursday, December 19, 9 p.m. to 5 a.m. Full closure of westbound Loop 1604 collector ramp at I-35 interchange for column cap setting. Traffic should follow detour signs.
Westbound
- Sunday, December 15, until Saturday, December 21, 9 p.m. to 7 a.m. Alternating lane closures of westbound Loop 1604 mainlanes from Pat Booker Road to Nacogdoches Road for bridge deck and barrier work.
- Sunday, December 15, until Saturday, December 21, 9 p.m. to 7 a.m. Full closure of westbound Loop 1604 frontage road from Gateway Boulevard to Gateway Place for bridge deck work. Traffic should follow detour signs.
- Monday, December 16, until Wednesday, December 18, 9 p.m. to 5 a.m. Full closure of Lookout Road and both turnarounds at Loop 1604 intersection for bridge deck work. Traffic should follow detour signs.
- Monday, December 16, until Thursday, December 19, 9 p.m. to 5 a.m. Full closure of westbound Loop 1604 mainlanes from Pat Booker Road to Lookout Road for bridge deck work. Traffic should follow detour signs.
- Monday, December 16, until Thursday, December 19, 9 p.m. to 5 a.m. Full closure of eastbound Loop 1604 connector ramp to northbound I-35 mainlanes for column cap setting. Traffic should follow detour signs.
I-35 from Loop 1604 to Toepperwein Road
Northbound
- Through Monday, February 3, long-term closure (24/7). Full closure on I-35 northbound collector exit ramp and left lane closure on I-35 northbound frontage road from Pat Booker Road to Loop 1604 for bridge work.
- Through Monday, February 3, long-term closure (24/7). Entrance ramp closure from Shin Oak Drive to Pat Booker Road for bridge work.
- Sunday, December 15, until Wednesday, December 18, 9 p.m. to 5 a.m. Multiple mainlane closures (3) of northbound I-35 from I-35 Access Road near Shin Oak Drive to Forum Parkway for striping, barrier, and temporary pavement work.
- Sunday, December 15, until Saturday, December 21, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road from Shin Oak Drive to Pat Booker Road for column and cap work. Traffic should follow detour signs.
- Sunday, December 15, until Saturday, December 21, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road, exit ramp, and entrance ramp from Pat Booker Road to Loop 1604 for bridge column and cap work. Traffic should follow detour signs.
- Sunday, December 15, until Saturday, December 21, 9 p.m. to 5 a.m. Full closure of eastbound and westbound lanes of Pat Booker Road at I-35 and northbound I-35 Pat Booker Road exit ramp for bridge column and cap work. Traffic should follow detour signs.
- Sunday, December 15, until Thursday, December 19, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road, exit ramp, and entrance ramp from Pat Booker Road to Loop 1604 interchange for bridge column and cap work. Traffic should follow detour signs.
- Sunday, December 15, until Saturday, December 21, 9 p.m. to 7 a.m. Multiple mainlane closures (3) on northbound I-35, multiple lane closures (2) on northbound I-35 frontage road and exit ramp closure from Toepperwein Road to Pat Booker Road for drilled shaft, column, and cap work.
- Monday, December 16, until Wednesday, December 18, 9 p.m. to 5 a.m. Full closure of I-35 Access Road bridge from I-35 northbound frontage road to I-35 southbound frontage road, near Shin Oak Drive for construction work. Traffic should follow detour signs.
- Monday, December 16, until Saturday, December 21, 9 p.m. to 5 a.m. Multiple mainlane closures (3) of northbound I-35 from I-35 Access Road near Shin Oak Drive to Forum Parkway for bridge structure work.
Southbound
- Through Monday, June 30, 2025, long-term closure (24/7). Left lane closure on southbound frontage road of I-35 from McMorris Boulevard to Pat Booker Road for construction.
- Sunday, December 15, until Friday, December 20, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and entrance ramp from Shin Oak Drive to Toepperwein Road for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Sunday, December 15, 9 p.m. to 5 a.m. Full closure of eastbound and westbound lanes of Toepperwein Road at I-35 for bridge deck work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Sunday, December 15, until Saturday, December 21, 9 p.m. to 7 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, entrance ramp closure, and exit ramp closure from Pat Booker Road to Toepperwein Road for bridge deck work.
- Monday, December 16, 9 p.m. to 5 a.m. Full closure of eastbound Loop 1604 mainlanes from Gateway Boulevard to Pat Booker Road, full closure of southbound I-35 collector ramp at Loop 1604 interchange for bridge deck work. Traffic should follow detour signs.
I-35 from Toepperwein Road to O’Connor Road
Northbound
- Sunday, December 15, until Saturday, December 21, 9 p.m. to 7 a.m. Multiple lane closures (3) on northbound mainlanes, multiple lane closures (2) on northbound I-35 frontage road and exit ramp closure from Judson Road to Toepperwein Road for drilled shaft, column, and cap work.
- Sunday, December 15, until Saturday, December 21, 9 p.m. to 7 a.m. Multiple lane closures (3) on northbound I-35 mainlanes, multiple lane closures (2) on northbound I-35 frontage road, exit ramp closure and entrance ramp closure from O’Connor Road to Judson Road for drilled shaft, column, and cap work.
- Sunday, December 15, until Wednesday, December 18, 9 p.m. to 5 a.m. Full closure on northbound I-35 frontage road, and entrance ramp from O’Connor Road to Judson Road for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Sunday, December 15, until Saturday, December 21, 9 p.m. to 7 a.m. Full closure of northbound I-35 frontage road and exit ramp from Judson Road to Toepperwein Road for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Sunday, December 15, until Saturday, December 21, 9 p.m. to 7 a.m. Full closure of northbound I-35 frontage road, and entrance ramp from O’Connor Road to Judson Road for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
Southbound
- Through Friday, January 3, 2025, long-term closure (24/7). Left lane closure on southbound frontage road of I-35 at Crownpoint Drive for construction work.
- Sunday, December 15, until Friday, December 20, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and exit ramp from Toepperwein Road to Judson Road for bridge deck work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Sunday, December 15, until Friday, December 20, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and entrance ramp from Judson Road to Crownpoint Drive for column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Sunday, December 15, until Friday, December 20, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and exit ramp closure from Crownpoint Drive to O’Connor Road for cap form erection work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Sunday, December 15, until Saturday, December 21, 9 p.m. to 7 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, entrance ramp closure, and exit ramp closure from Toepperwein Road to Judson Road for bridge deck work.
- Sunday, December 15, until Saturday, December 21, 9 p.m. to 7 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, entrance ramp closure, and exit ramp closure from Judson Road to O’Connor Road for drilled shaft, column, and cap work.
- Monday, December 16, until Friday, December 20, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and exit ramp from Toepperwein Road to Judson Road for bridge beam setting. Traffic should follow detour signs.
- Monday, December 16, until Friday, December 20, 9 p.m. to 5 a.m. Multiple lane closures (2) on southbound I-35 frontage road from Toepperwein Road to Judson Road for bridge beam setting.
I-35 from O’Connor Road to Thousand Oaks Drive
Northbound
- Through Saturday, December 21, long-term closure (24/7). Left lane closure on northbound frontage road of I-35 from Starlight Terrace to Weidner Road for construction work.
- Through Saturday, December 21, long-term closure (24/7). Left lane closure on northbound frontage road of I-35 from Weidner Road to O'Connor Road for construction work.
- Sunday, December 15, until Saturday, December 21, 9 p.m. to 7 a.m. Multiple lane closures (3) of northbound I-35 mainlanes, multiple lane closures (2) of northbound I-35 frontage road, right lane closure of eastbound O’Connor Road at I-35 intersection, entrance ramp closure, and exit ramp closure from Weidner Road to O’Connor Road for drainage and drilled shaft work.
- Sunday, December 15, until Saturday, December 21, 9 p.m. to 7 a.m. Multiple lane closures (3) on northbound I-35 mainlanes, alternating lane closures (2) on northbound I-35 frontage road and exit ramp closure from Thousand Oaks Drive to Weidner Road for drainage and drilled shaft work.
- Sunday, December 15, until Saturday, December 21, 9 p.m. to 7 a.m. Full closure of northbound I-35 frontage road, entrance ramp, and exit ramp from Starlight Terrace to Weidner Road, southbound to northbound turnaround at I-35 and Starlight Terrace intersection, northbound to southbound turnaround at I-35 and Weidner Road intersection for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
Southbound
- Through Saturday, December 21, long-term closure (24/7). Right lane closure on southbound frontage road of I-35 from Weidner Road to Thousand Oaks Drive for bridge work.
- Through Thursday, May 22, 2025, long-term closure (24/7). Entrance ramp closure on southbound I-35 from O’Connor Road for bridge work.
- Through Monday, February 24, 2025, long-term closure (24/7). Exit ramp closure on I-35 southbound frontage road from Weidner Road for construction work.
- Sunday, December 15, until Saturday, December 21, 9 p.m. to 5 a.m. Full closure on southbound frontage road, entrance ramp closure, and exit ramp closure of I-35 from Weidner Road to Thousand Oaks Drive for column work. Traffic should follow detour signs.
- Sunday, December 15, until Friday, December 20, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road from O’Connor Road to Tech Com Drive for drilled shaft, column, and cap work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Sunday, December 15, until Friday, December 20, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road and exit ramp from Tech Com Drive to Weidner Road for cap form erection work. Accommodations will be made for local traffic. Traffic should follow detour signs.
- Sunday, December 15, until Friday, December 20, 9 p.m. to 5 a.m. Full closure on southbound I-35 frontage road, entrance ramp closure, and exit ramp from Weidner Road to Thousand Oaks Drive for sidewalk and curb installation work. Traffic should follow detour signs.
- Sunday, December 15, until Saturday, December 21, 9 p.m. to 7 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, alternating lane closures (2) on southbound I-35 frontage road, entrance ramp closure, and exit ramp closure from O’Connor Road to Weidner Road for drilled shaft, column, and cap work.
- Sunday, December 15, until Saturday, December 21, 9 p.m. to 7 a.m. Multiple lane closures (3) on southbound I-35 mainlanes, multiple lane closures (2) on southbound I-35 frontage road, entrance ramp closure, and exit ramp closure from Weidner Road to Thousand Oaks Drive for drainage and drilled shaft work.
- Sunday, December 15, until Saturday, December 21, 9 p.m. to 5 a.m. Full closure on southbound frontage road, exit ramp closure of I-35 from Thousand Oaks Drive to Randolph Boulevard and northbound to southbound turnaround closure at I-35 and Thousand Oaks Drive for Utilities. Traffic should follow detour signs.
- Sunday, December 15, until Saturday, December 21, 9 a.m. to 3 p.m. Right turn lane closure on southbound frontage road of I-35 at Weidner Road and right Lane closure on westbound Weidner Road from southbound frontage road of I-35 to N Weidner Road for utilities work.
I-35 from Thousand Oaks Drive to I-410 North Interchange
Northbound
- Through Tuesday, December 17. Left lane closure on northbound frontage road of I-35 from Randolph Boulevard to Starlight Terrace for bridge work.
- Sunday, December 15, until Saturday, December 21, 9 p.m. to 5 a.m. Full closure of northbound I-35 frontage road from Crestway Drive to Weidner Road and full closure of Starlight Terrace at I-35 intersection for drainage and drilled shaft work. Traffic should follow detour signs.
- Sunday, December 15, until Saturday, December 21, 9 p.m. to 5 a.m. Full closure of northbound I-35 connector ramp to mainlanes of westbound I-410 and entrance ramp closure from Randolph Boulevard to the mainlanes of westbound I-410 for bridge deck and cap work. Traffic should follow detour signs.
Southbound
- Through Tuesday, April 1, 2025, long-term closure (24/7). Alternating lane closures on southbound I-35 frontage road between Thousand Oaks Drive and Whirlwind Drive for roadway reconstruction and structural work.
- Through Saturday, February 1, 2025, long-term closure (24/7). Southbound to northbound turnaround closure at Thousand Oaks for construction work.
- Sunday, December 15, until Saturday, December 21, 9 p.m. to 5 a.m. Full closure of southbound I-35 frontage road and exit ramp from Thousand Oaks Drive to Randolph Boulevard, and northbound to southbound turnaround at I-35 and Thousand Oaks Drive for column, and cap work. Traffic should follow detour signs.
I-410 North from Starcrest Drive to Harry Wurzbach Road
Eastbound
- Sunday, December 15, until Saturday, December 21, 9 p.m. to 5 a.m. Full closure of eastbound I-410 frontage road, and entrance ramp closure from Harry Wurzbach Road to Ira Lee Road, and westbound to eastbound turnaround at Harry Wurzbach Road and I-35 intersection, and eastbound frontage road bypass closure of I-410 from Harry Wurzbach Road to Ira Lee Road for a traffic shift and drilled shaft work. Traffic should follow detour signs.
Westbound
- Monday, December 16, until Thursday, December 19, 9 a.m. to 3 p.m. Right lane closure of westbound I-410 frontage road from Norwich Drive to Nacogdoches Road for traffic signal equipment installation work.
I-410 North from I-35 Interchange to Starcrest Drive
Eastbound
- Sunday, December 15, until Saturday, December 21, 9 p.m. to 7 a.m. Full closure of eastbound I-410 connector ramp to northbound mainlanes of I-35 for cap work. Traffic should follow detour signs.
- Sunday, December 15, until Saturday, December 21, 9 p.m. to 7 a.m. Full closure of eastbound frontage to westbound frontage connector ramp of I-410 from Austin Highway (Loop 368) to Perrin Creek, full closure of southbound frontage road of I-35 from Randolph Boulevard to Perrin Creek and full closure of northbound frontage road to westbound frontage road of I-410 at Perrin Creek for cap work. Traffic should use detour signs.
- Sunday, December 15, until Saturday, December 21, 9 p.m. to 7 a.m. Exit ramp closure on eastbound I-410 to Starcrest Drive and Perrin Beitel for traffic shift work. Traffic should use previous exit and entrance ramps.
Westbound
- Through Tuesday, April 1, 2025, long-term closure (24/7). Left lane closure on westbound frontage road of I-410 from Perrin Creek to Austin Highway (Loop 368) for construction.
- Sunday, December 15, until Saturday, December 21, 9 p.m. to 7 a.m. Full closure on westbound frontage road of I-410 and exit ramp from Perrin Creek to Perrin Beitel, and connector ramp closure from northbound Austin Highway (Loop 368) to I-410 westbound frontage road for bridge deck work. Traffic should follow detour signs.
- Sunday, December 15, until Saturday, December 21, 9 p.m. to 5 a.m. Exit ramp closure from westbound I-410 mainlanes to southbound Austin Highway (Loop 368) for cap work. Traffic should use next exit ramp.
- Sunday, December 15, until Saturday, December 21, 9 p.m. to 7 a.m. Full closure of entrance ramp on westbound frontage road of I-410 from Perrin Creek to Perrin Beitel and exit ramp closure to Austin Highway (Loop 368) from southbound I-35 connector ramp to westbound I-410 for cap work. Traffic should follow detour signs.
I-35 from I-410 North Interchange to Walzem Road
Northbound
- Sunday, December 15, until Saturday, December 21, 9 p.m. to 7 a.m. Southbound to northbound turnaround closure at Walzem Road and I-35, alternating lane closures (2) on northbound frontage road, and alternating entrance and exit ramp closures of I-35 from Walzem Road to Crestway Drive for cap work. Traffic should follow detour signs.
Southbound
- Sunday, December 15, until Saturday, December 21, 9 p.m. to 5 a.m. Full closure on southbound frontage road, exit ramp, and entrance ramp of I-35 from Randolph Boulevard to Walzem Road for deck work. Traffic should follow detour signs.
- Monday, December 16, until Saturday, December 21, 9 p.m. to 5 a.m. Full closure of southbound I-35 frontage road from Randolph Boulevard to Fratt Road and full closure of Randolph Boulevard at I-35 intersection for drilled shaft work. Traffic should follow detour signs.
I-35 from Walzem Road to Eisenhauer Road
Northbound
- Monday, December 16, until Friday, December 20, 9 p.m. to 5 a.m. Left lane closure on northbound I-35 mainlanes from Goldfield Drive to Walzem Road for pavement work.
- Monday, December 16, until Friday, December 20, 9 p.m. to 5 a.m. Left lane closure on northbound I-35 frontage road from Galahad Drive to Walzem Road for barrier work.
- Monday, December 16, until Friday, December 20, 9 p.m. to 5 a.m. Multiple right lane closures (2) on northbound I-35 mainlanes from Galahad Drive to Walzem Road for barrier work.
- Monday, December 16, until Friday, December 20, 9 p.m. to 5 a.m. Entrance ramp closure on northbound I-35 frontage road between Eisenhauer Road and Walzem Road for barrier work. Traffic should use next entrance ramp.
- Monday, December 16, until Friday, December 20, 9 p.m. to 5 a.m. Northbound to southbound I-35 turnaround closure at Walzem Road for barrier work.
- Wednesday, December 18, until Friday, December 20, 9 p.m. to 5 a.m. Left lane closure on northbound I-35 frontage road from Eisenhauer Road to Galahad Drive for cap work.
- Wednesday, December 18, until Friday, December 20, 9 p.m. to 5 a.m. Right lane closure on northbound I-35 mainlanes from Eisenhauer Road to Galahad Drive for cap work.
- Wednesday, December 18, until Friday, December 20, 9 p.m. to 5 a.m. Exit ramp closure on northbound I-35 mainlanes to Walzem Road for cap work. Traffic should use prior exit ramp.
- Friday, December 20, 11 p.m. to 7 a.m. Left lane closure on northbound I-35 mainlanes from Goldfield Drive to Walzem Road for pavement work.
- Friday, December 20, 11 p.m. to 7 a.m. Left lane closure on northbound I-35 frontage road from Galahad Drive to Walzem Road for barrier work.
- Friday, December 20, 11 p.m. to 7 a.m. Multiple right lane closures (2) on northbound I-35 mainlanes from Galahad Drive to Walzem Road for barrier work.
- Friday, December 20, 11 p.m. to 7 a.m. Entrance ramp closure on northbound I-35 frontage road between Eisenhauer Road and Walzem Road for barrier work. Traffic should use next entrance ramp.
- Friday, December 20, 11 p.m. to 7 a.m. Northbound to southbound I-35 turnaround closure at Walzem Road for barrier work.
- Friday, December 20, 11 p.m. to 7 a.m. Left lane closure on northbound I-35 frontage road from Eisenhauer Road to Galahad Drive for cap work.
- Friday, December 20, 11 p.m. to 7 a.m. Right lane closure on northbound I-35 mainlanes from Eisenhauer Road to Galahad Drive for cap work.
I-35 from Rittiman Road to I-410 South Interchange
Southbound
- Monday, December 16, until Friday, December 20, 9 p.m. to 5 a.m. Multiple right lane closures (2) on southbound I-35 mainlanes from Rittiman Road to Petroleum Drive for drilled shaft work.
- Friday, December 20, 11 p.m. to 7 a.m. Multiple right lane closures (2) on southbound I-35 mainlanes from Rittiman Road to Petroleum Drive for drilled shaft work.
I-35 and I-410 South Interchange
Northbound
- Monday, December 16, until Friday, December 20, 7 a.m. to 5 p.m. Full closure on northbound Industry Park Drive from Space Center Drive to Goldfield Drive for utilities work.
I-35 from I-410 South to Petroleum Drive
Northbound
- Monday, December 16, until Friday, December 20, 9 p.m. to 5 a.m. Multiple lane closures (2) on northbound and southbound I-35 mainlanes from George Beach Avenue to Walzem Road and on I-410 from Binz Engleman Road to Space Center Drive for pavement work.
- Friday, December 20, 11 p.m. to 7 a.m. Multiple lane closures (2) on northbound and southbound I-35 mainlanes from George Beach Avenue to Walzem Road and on I-410 from Binz Engleman Road to Space Center Drive for pavement work.
I-410 South from I-35 to Binz Engleman Road
Northbound
- Sunday, December 15, until Friday, December 20, 9 p.m. to 5 a.m. Rolling closure on northbound and southbound mainlanes of I-35 from George Beach Avenue to Walzem Road and I-410 from Binz Engleman Road to Space Center Drive for sweeping and debris work.
- Friday, December 20, 11 p.m. to 7 a.m. Rolling closure on northbound and southbound mainlanes of I-35 from George Beach Avenue to Walzem Road and I-410 from Binz Engleman Road to Space Center Drive for sweeping and debris work.
OTHER LANE CLOSURES
- For your information, there are other lane closures underway within the I-35 NEX project this week, but they are not expected to affect traffic or create notable delays.
|