My 35 Central Texas News: Volume 2, Number 3

My Interstate 35 - Central Texas News
 
IN THIS ISSUE

April 2012

RECENT SAFETY TRAINING PAYS OFF

SAFETY IS JOB ONE: I-35 CONSTRUCTION FROM THE GROUND UP

MILE MARKERS: MORE THAN A MEASURE

Sign Up

CALENDAR

April 5: Section 3A-1 Groundbreaking

10 a.m. in Troy at southwest corner of Main St./FM 935 & I-35 intersection

April 5: Shippers Advisory Group Meeting

2 p.m. in Temple, TX

April 5: Open-House Public Information Meeting on the Proposed I-35 On- and Off-Ramp Changes between Midway Drive & S. Loop 363

5-7 p.m. at the
Railroad & Heritage Museum
315 West Avenue B
Temple, TX

April 19: District-Wide Emergency Responders Meeting

11:30 a.m. in Waco, TX

April 26: TxDOT's Interactive Work Zone Awareness Event

10 a.m.-2 p.m.
Freightliner Parking Area (northbound I-35 between
N. Loop 340 and Craven Ave., just north of Waco)

May 8: Community Visioning Celebration and Expo

TxDOT Booth & Display
5-7 p.m.
Waco Convention Center
Waco, TX

May 9: Presentation for West Kiwanis Club

11:45 a.m.
West Senior Center
West, TX

May 24: Preconstruction Meeting for Section 3A-2

10 a.m. - 2 p.m.
Temple, TX

April-June: Upcoming Business Community Meetings

April 25, 2012, 3-5 p.m.
Hill / McLennan County West Community Center
West, TX | Directions

May 23, 2012, 3-5 p.m. McLennan County
Greater Waco Chamber of Commerce
Waco, TX | Directions

June 21, 2012, 3-5 p.m.
Bell County Central Texas Council of Governments
Belton, TX | Directions

LINKS

FEDERAL HIGHWAY ADMINISTRATION

MY35.ORG

TXDOT

CONTACT

Jodi Wheatley

I-35 Information Specialist
TxDOT Waco District
100 S. Loop Dr.
Waco, TX 76704
254/867-2836
jodi.wheatley@txdot.gov

I-35 in Central Texas map

 

 

 

 

RECENT SAFETY TRAINING PAYS OFF

A recent training course for law enforcement in work zones is already paying off. | Read More

SAFETY IS JOB ONE: I-35 CONSTRUCTION FROM THE GROUND UP

Years from now, safety experts may point to the I-35 Expansion Project as the beginning of a sweeping cultural change in the Texas road-construction industry. Or at least that's the hope of TxDOT Safety Officer Jim Busby. For the first time in Texas — at Busby's suggestion — safety requirements have been built into construction contracts. | Read More

MILE MARKERS: MORE THAN A MEASURE

The lowly mile marker. You sometimes see it. You probably ignore it. Turns out, mile markers do more than just measure the roadway. | Read More

CONSTRUCTION UPDATES

SECTION 1B: SALADO

(FM 2843 TO FM 2484)

Access this section's project map (schematic).

Down the Road

  • Continue ROW acquisition and utility relocation. 
  • Start construction in early May.

SECTION 1C: SALADO TO BELTON

(FM 2484 TO US 190/FM 436)

Access this section's project map (schematic).

Lane Closures

  • East Amity Rd. is closed from the I-35 northbound frontage road to Rose Ln. until the end of April.
  • The I-35 northbound frontage road at Amity Rd. will be closed April 9-24 while the contractor connects the I-35 northbound frontage road intersection approach to the new Amity crossover bridge. Detour signs will be in place.
  • The Connell Street exit ramp from US 190 W (first exit after entering US 190 from southbound I-35) has been permanently closed to allow construction of the new flyover connecting I-35 northbound to US 190 W.
  • The inside lane of the US 190 W access road from I-35 to Connell Street is closed to allow construction of flyover support columns.

Milestones

  • Beams have been set for the I-35 northbound frontage-road bridge over the Lampasas River.

Down the Road

  • Continue work on northbound frontage road from Amity Rd. to Loop 121.
  • Continue work on southbound frontage road from US 190 to Loop 121.
  • Continue work on guard rail on the crossover structures. 
  • Continue work on intersection approaches to the crossovers.
  • Pour bridge deck for Phase 1 portion of the Loop 121 crossover.
  • Pour bridge deck for the northbound frontage-road bridge over the Lampasas River.

SECTION 3A-1: TEMPLE TO TROY

(N. LOOP 363 TO N. TROY CITY LIMIT))

Access this section's project map (schematic).

Down the Road

  • Groundbreaking scheduled for April 5 at 10 a.m.

SECTION 3B: LORENA TO HEWITT

(WOODLAWN RD. TO SUN VALLEY BLVD./FM 2063)

Access this section's project map (schematic).

Milestones

  • Groundbreaking held March 14 with Congressman Bill Flores, Transportation Commissioner Jeff Austin, State Rep. "Doc" Anderson and a number of city and county officials.

Down the Road

  • Begin work on new crossovers and intersections at S. FM 2837, N. FM 2837 and FM 1695.

BRAZOS RIVER BRIDGES (WACO)

Access this section's project map (schematic).

Down the Road

  • Construction expected to start in late summer 2012.

SECTION 3C: HEWITT TO WACO

(FM 2063/SUN VALLEY BLVD. TO S. LOOP 340)

Milestones

  • Construction work completed.

Down the Road

  • Continue vegetative establishment and plant maintenance.

SECTION 5A: WACO TO WEST

(N. LOOP 340 TO FM 1858)

Lane Closures

  • The Wiggins Rd. crossover is closed for demolition and is expected to be closed for 12-18 months. Tours Rd. (next crossing to the south) and Tokio Rd. (next crossing to the north) are open.
  • Main St. in Elm Mott is permanently closed to through traffic at the southbound frontage road.

Milestones

  • Beams have been set on the UPRR overpass.
  • Beams have been set for the new FM 1858 crossover.
  • Opened the new northbound exit ramp to Craven Ave.; closed the old ramp.
  • Opened the new southbound entrance ramp from Craven Ave.; closed the old ramp.
  • Started the new turnarounds at the Meyers crossing.

Down the Road

  • Set retaining wall panels for the FM 1858 crossover.
  • Set retaining wall panels and pour bridge deck for the UPRR overpass.
  • Continue constructing the northbound frontage road between Wiggins Rd. and FM 1858.
  • Switch the southbound mainlane traffic to the new section of the BUS 77 overpass.
  • Remove the old Craven Ave. exit and entrance ramps.
  • Switch the southbound frontage road traffic to new concrete pavement between Craven Ave. and Meyers Ln.
  • Open the new northbound exit ramp to Crest Dr.
  • Begin construction on the Craven intersection.
  • Begin constructing support columns and caps for new southbound overpasses at BUS 77 and FM 308.

SECTION 5B: WEST TO ABBOTT

(FM 1858/TOKIO RD. TO FM 1304)

Access this section's project map (schematic).

Milestones

  • Installed retaining walls at Marable St.
  • Extended existing box culverts.
  • Began placing embankment at County Line Rd.

Down the Road

  • Pour caps for the support columns under Marable St. overpass.
  • Cut ground for the new southbound frontage road and begin placing road base between Marable St. and County Line Rd.
  • Continue utility relocations.
  • Pave northbound and southbound detour lanes from 1/2 mi. south of FM 1242 to FM 1304, shifting traffic onto those lanes to begin work on inside section of mainlanes.
  • Install retaining walls at County Line Rd. and HCR 3102.
  • Continue extending box culverts.

SECTION 5C: ABBOTT TO SOUTH OF HILLSBORO

(FM 1304 TO FM 310)

Milestones

  • Poured the southbound Cobb Creek mainlane bridge deck.
  • Backfilled pavement edges; began seeding.

Down the Road

  • Complete and open new ramps on the northbound side.
  • Pour rail for mainlane Cobb Creek bridge.
  • Remove the traffic barrier from mainlane shoulders.
  • Resume laying asphalt for both the northbound and southbound frontage roads.
  • Begin installing permanent pavement markings.

SAFETY REST AREAS (HILL COUNTY)

Milestones

  • The embankment for service roads is over 90 percent completed.

Down the Road

  • Continue preparing to pour slab for the northbound site.
  • Begin work on the southbound-side building.

 