July 9, 2025
Rainier Ave S Phase 4 Improvements Construction Update
S. 2nd St. Closed from Lake Ave. S. to Rainier Ave. S.
-
S. 2nd St will be closed for the next month
Suggested routes to consider when commuting:
- For Northbound traffic on Rainier, traffic could take Lake Ave. S.
- For Southbound traffic on Rainier, traffic could take Shattuck Ave. S.
Lane closures will increase significantly as embankment and phases of construction continue. We will do our best to notify the public of any closures within 24 hours.
Please note: Paving work is subject to weather conditions. Local access will be maintained during these temporary closures, and temporary barricades will be set up for safe passage.
Getting around during construction
With the summer season upon us, please know that local events may further impact traffic. For the latest information, we recommend checking the City of Renton events and Visit Renton calendar to help plan your trips accordingly.
For Renton traffic impacts for the week, visit rentonwa.gov/traffic. As part of the I-405/Renton to Bellevue Widening project, the Washington State Department of Transportation (WSDOT) has several closures this summer that may impact overall traffic flow. Visit WSDOT's website for upcoming closures on I-405.
Temporary crosswalks and access points will be provided as needed until the full sidewalk installation is completed.
Please follow all pedestrian and traffic controls as work progresses.
Business Spotlight
Gravity Sports – 126 Rainier Ave S.
Summer Vibes & Local Rides: This week, we’re spotlighting Gravity Sports, a cornerstone of the Renton community since 1976. For nearly 50 years, this family-owned shop has outfitted generations of skaters, snowboarders, and surfers with top-quality gear and expert advice. Located in the same spot on Rainier Avenue since day one, Gravity Sports is your go-to destination for all things roll, ride, and glide. Whether you’re picking up your first board, upgrading your setup, or just browsing the latest gear, they’ve got you covered.
🎥 Watch the highlight video featuring Gravity Sports here: https://youtu.be/EgtmJ_6p2Z0

Week of July 7 and July 14
Ongoing work along the corridor and project area, including:
-
Curb, gutter, and sidewalk work continues
-
Grading and paving of driveways
-
Paving roadways
For the full 5 week look-ahead schedule please visit the project webpage.
Stay connected
Visit the City’s project webpage to learn more about the project and sign up for email updates to be informed of construction activities and project updates.
Still have questions? Get in touch with the project outreach team
Call the project hotline, monitored Monday through Friday from 9 a.m. to 5 p.m. at 425-224-2446 or email us at info@rainierconstruction.org with any questions or comments.
You are receiving this message because you have expressed interest in receiving news and information on the Rainier Ave S. Phase 4 project. You may unsubscribe below if you no longer wish to receive our newsletter.
|