Downtown Renton Construction: Temporary two-way cul-de-sac on Wells Ave S
City of Renton sent this bulletin at 07/06/2021 05:38 PM CDTHi,
As part of the ongoing utility work, we plan to test and connect to an existing water main on S 2nd St. Given the complexity of this work, we’re planning to expand the work zone starting tomorrow. During this work, Wells Ave S will temporarily operate as a two-way cul-de-sac between S 2nd St and S 3rd St to maintain access to local businesses.
In the meantime, please don’t hesitate to call 425-363-1007 if you have questions or you need assistance with large deliveries.
![]() |
What does local and business access mean? Anyone can still drive and park on the block leading up to the intersection. You just can’t drive through the intersection. |
Noted street closures are daytime closures during construction hours. A minimum of one lane will be open on S 3rd St after construction hours. Please follow posted signs and directions from flaggers for safe access. |
Thank you, and if you have any questions, please don’t hesitate to call us at 425-363-1007 or email wellswilliams@rentonwa.gov or duip@rentonwa.gov.
![]() |