Altman Road (between Oxbow Drive and Pipeline Road) through November 1, 2026: Daytime closure with one lane of south-only traffic outside work hours.
-
Oxbow Drive/Altman Road intersection 24/7 closure from November 2-25 and November 30-December 24, 2026: Full closure of the intersection. Through traffic will be detoured to Lusted and Hosner roads. Intersection closure may extend through January 2027.
-
Dodge Park Boulevard (from east of Altman Road to Cottrell Road) through January 31, 2027: Single-lane with flagging during work hours. After work hours, normal traffic will resume.
-
Cottrell Road to Lusted Road, Hosner Road, and Oxbow Drive through January 2027: Expect increased haul truck traffic on this route as clean fill is transported to a fill site on Oxbow Drive east of the Oxbow/Altman intersection.
-
Bluff Road (at Proctor Road and 362nd Avenue intersection) through November 30, 2026: Intermittent single-lane restriction with two-way flagging Mon.-Sat. between 8:15 a.m.-2:15 p.m.
Other work happening the week of November 2
Staff will be at the project work sites during shift hours to perform various tasks. Work hours will be between 7 a.m. and 6 p.m., Monday through Saturday.
Filtration facility site activities include:
- Ongoing construction traffic traveling to and from the site, including concrete trucks, soil off hauling, and bussing for craftworkers
- Delivering equipment and materials to the site
- Placing concrete for treatment process areas and buildings
- Installing roofing and siding for buildings
- Installing new water pipeline at the site
- Ongoing stormwater management and erosion control
- Lighting for safety and maintenance activities
- As needed street sweeping
Emergency access road activities include:
- Installing new water line in the access road
Raw water tunnel/pipeline site activities include:
- Excavating two 1,245-foot pipeline tunnels and installing new pipeline in the Water Bureau's easement between Lusted Road and the facility site
- Ongoing stormwater management and erosion control
- Noise and vibration during work hours
Finished water pipeline site activities include:
- Delivering equipment and materials to the work areas
- Installing new water pipeline on the south shoulder of Dodge Park Boulevard
- Installing new water pipeline at the Oxbow Drive and Altman Road intersection
- Ongoing stormwater management and erosion control
- As needed street sweeping
Finished water intertie site activities include:
- Excavating and preparing to install pipe
- Ongoing stormwater management and erosion control
Work schedules are subject to change depending on weather and other field conditions.
Upcoming traffic impacts
Please note that some planned traffic restrictions are pending county approval.
-
Cottrell Road (between Carpenter Lane and Bluff Road) intermittent two-way flagging while tree work is occurring—estimated mid-November 2026
-
Altman Road/Pipeline Road intersection and Altman Road (between Oxbow Drive and Pipeline Road) 24/7 closure—late November 2026-July 2027
Bull Run Filtration: coffee with the contractor
We will host an informal drop-in session where project neighbors can chat with representatives of the facility and pipeline construction teams, ask questions, and hear about recent progress and upcoming work. There is no presentation, so stop in anytime between 9 and 10:30 a.m.
Date: Thursday, November 12, 2026
Time: 9-10:30 a.m. (drop in)
Location: Multnomah County Grange #71, 30639 SE Bluff Road, Gresham
Can't make it this time? Join us for the in-person Coffee with the Contractor in DecemberCoffee with the Contractor in December.
|
|
Get construction text alerts
Sign up to receive text notifications about temporary lane closures and other construction traffic information related to the Bull Run Filtration project.
|
|
|
The Bull Run Filtration Project will remove Cryptosporidium and other contaminants from the Bull Run water supply, producing cleaner, safer water for the roughly 840,000 people who use our water today and for future generations. The project is required by the federal Safe Drinking Water Act and must be in operation by September 30, 2029, through a Bilateral Compliance Agreement with the Oregon Health Authority.
To learn more, visit portland.gov/water/filtration.
|
|
|
Know someone who would be interested in updates about the Bull Run Treatment Projects? Please share the news!

The City of Portland is committed to providing meaningful access. To request translation, interpretation, modifications, accommodations, or other auxiliary aids or services, or to file a complaint of discrimination, contact 503-823-4000 (311), Relay Service & TTY: 711
Traducción e Interpretación | Biên Dịch và Thông Dịch | अनुवादन तथा व्याख्या 口笔译服务 | Устный и письменный перевод | Turjumaad iyo Fasiraad Письмовий і усний переклад | Traducere și interpretariat | Chiaku me Awewen Kapas Translation and Interpretation: 503-823-4000 (311), Relay: 711
This email was sent from an unmonitored inbox. Please do not reply. Instead, contact us at bullrunprojects@portlandoregon.gov.
|
|
|
|