No construction activities are planned Saturday September 5-Monday September 7 in observance of Labor Day.
 Current traffic impacts
-
Lusted Road (just north of county line) through October 17, 2026: Closure during work hours with two-way traffic managed by temporary traffic signals outside work hours. During work hours, residents will be able to travel either north or south of the closure. Through traffic will be detoured to Dodge Park Boulevard and Cottrell Road.
-
Dodge Park Boulevard (Cottrell Road to about 1500 feet east of intersection) September 3, 2026-October 31, 2026: Single-lane with flagging during work hours. After work hours, normal traffic will resume.
What to expect:
- Local and emergency access will be maintained
Controlled blasts during pipeline shaft excavation
Our contractors are using some scheduled, controlled blasts to excavate the pipeline shaft in the southeast corner of the filtration facility site. Each blast lasts a few seconds and noise and vibration during each blast is monitored. Safety measures are in place throughout the work and all controlled blasts have been within safety standards.
Five controlled blasts have occurred. One to two more are anticipated. Controlled blasts will be scheduled on weekdays between 9 a.m. and 4 p.m. and may be spaced over several weeks. Dates and times are subject to change depending on progress.
Project neighbors can sign up for pre-blast notices at portland.gov/brtpnews.
View more info about controlled blasts on the project construction webpage.
Other work happening the week of August 31
Staff will be at the project work sites during shift hours to perform various tasks. Work hours will be between 7 a.m. and 6 p.m., Monday through Saturday.
Filtration facility site activities include:
- Ongoing construction traffic traveling to and from the site, including bussing for craftworkers
- Delivering equipment and materials to the site
- Placing concrete for treatment process areas and buildings
- Installing structural steel and masonry walls for buildings
- Installing new water pipeline at the site
- Excavating 237-foot-deep raw water pipeline shaft at southeast corner of facility site
- Ongoing stormwater management and erosion control
- Lighting for safety and maintenance activities
- As needed street sweeping
Emergency access road activities include:
- Completing initial potholing and installing silt fence ahead of construction
- Preparing to excavate the current farm access road and install a new subgrade
Raw water tunnel/pipeline site activities include:
- Excavating two 1,245-foot pipeline tunnels
- Completing pipeline work and preparing for repaving of Lusted Road work area
- Ongoing stormwater management and erosion control
- Noise and vibration through summer
Finished water pipeline site activities include:
- Delivering equipment and materials to the work areas
- Installing new water pipeline on the south shoulder of Dodge Park Boulevard
- Installing vaults and other pipe appurtenances in the Water Bureau's easement between Lusted Road and Dodge Park Boulevard
- Ongoing stormwater management and erosion control
- As needed street sweeping
Finished water intertie site activities include:
- Installing pipe supports inside the new facility
- Ongoing stormwater management and erosion control
Work schedules are subject to change depending on weather and other field conditions.
Upcoming traffic impacts
Please note that some planned traffic restrictions are pending county approval.
-
Dodge Park Boulevard (between Altman Road and Cottrell Road) single-lane restriction with flagging during work hours—estimated September 14, 2026-December 24, 2026
-
Altman Road (between Oxbow Drive and Pipeline Road) single-lane restriction with 24/7 south-only traffic—estimated September 21-30, 2026
-
Oxbow Drive/Altman Road intersection 24/7 closure with through traffic detoured to Pipeline, Lusted, and Hosner roads (see map below)—estimated October 1-29 and November 2-25, 2026
Bull Run Filtration: coffee with the contractor
The Water Bureau will host an informal drop-in session where project neighbors can chat with representatives of the facility and pipeline construction teams, ask questions, and hear about recent progress and upcoming work. There is no presentation, so stop in anytime between 9 and 10:30 a.m.
Date: Thursday, September 10, 2026
Time: 9 a.m. to 10:30 a.m. (drop in)
Where: Multnomah County Grange #71, 30639 SE Bluff Road, Gresham
Can't make it this time? Join us for the next online Neighbor Update Meeting October 8.
|
|
Get construction text alerts
Sign up to receive text notifications about temporary lane closures and other construction traffic information related to the Bull Run Filtration project.
|
|
|
The Bull Run Filtration Project will remove Cryptosporidium and other contaminants from the Bull Run water supply, producing cleaner, safer water for the roughly 840,000 people who use our water today and for future generations. The project is required by the federal Safe Drinking Water Act and must be in operation by September 30, 2029, through a Bilateral Compliance Agreement with the Oregon Health Authority.
To learn more, visit portland.gov/water/filtration.
|
|
|
Know someone who would be interested in updates about the Bull Run Treatment Projects? Please share the news!

The City of Portland is committed to providing meaningful access. To request translation, interpretation, modifications, accommodations, or other auxiliary aids or services, or to file a complaint of discrimination, contact 503-823-4000 (311), Relay Service & TTY: 711
Traducción e Interpretación | Biên Dịch và Thông Dịch | अनुवादन तथा व्याख्या 口笔译服务 | Устный и письменный перевод | Turjumaad iyo Fasiraad Письмовий і усний переклад | Traducere și interpretariat | Chiaku me Awewen Kapas Translation and Interpretation: 503-823-4000 (311), Relay: 711
This email was sent from an unmonitored inbox. Please do not reply. Instead, contact us at bullrunprojects@portlandoregon.gov.
|
|
|
|