April construction update
|
|
|
The Water Bureau is installing 3,350 feet of water main (pipe) in Southwest Portland.
 Work is continuing in small areas along the construction route.
Final road work
You may notice periods of inactivity and rough roads during some stages of this project. We will clean up the project site and repair any damage from construction at the end of the project.
|
|
|
During paving, crews will:
-
Restore the roads to their original condition where we dug trenches
-
Pour concrete to repair curbs and sidewalks affected by construction
-
Restore vegetation that was disturbed during construction
|
|
|
This project will return roadways and pedestrian areas to pre-construction condition. Pre-construction condition will be determined using survey information and photo and video recorded before work began.
This project does not include any additional road improvements like adding speed bumps, sidewalks, or traffic signals, or paving unimproved gravel roads.
|
|
We have installed about 85 percent of new water pipes along SW Nevada Street, SW Fifth Avenue, and SW Chestnut Street. Work is continuing in small areas along these roads.
Pipe installations
Crews are now installing a water main (pipe) at South Corbett Avenue near South Laview Drive. During this phase, crews will:
-
Dig trenches for the new water pipe
-
Temporarily cover open trenches each evening while work is in progress
Underground drilling is complete
Crews have finished installing water pipe underneath SW Barbur Boulevard, SW Brier Place, and I5.
Pipe connections
There are still some key steps required before we can finish this project. Now that the new water pipes have been installed, crews will:
|
|
-
Flush the new pipes with chlorinated water to sanitize them
-
Test the pipes to ensure they are sanitized
-
Connect the pipes to the water system
|
|
|
Crews will work to complete other utility work before final paving begins. No water shutoffs are expected for this work.
Experiencing a water emergency? Contact our 24-hour emergency line at 503-823-4874 or portland.gov/water/service-problem
|
|
|
The City of Portland is committed to providing meaningful access. To request translation, interpretation, modifications, accommodations, or other auxiliary aids or services, or to file a complaint of discrimination, contact 503-823-4000 (311), Relay Service & TTY: 711
Traducción e Interpretación | Biên Dịch và Thông Dịch | अनुवादन तथा व्याख्या 口笔译服务 | Устный и письменный перевод | Turjumaad iyo Fasiraad Письмовий і усний переклад | Traducere și interpretariat | Chiaku me Awewen Kapas Translation and Interpretation: 503-823-4000 (311), Relay: 711
This email was sent from an unmonitored inbox. Please do not reply. Instead, contact us at waterprojects@portlandoregon.gov.
|
|
|
|