 Traffic impacts
-
Altman Road (between Lusted Road and Pipeline Road): Flagged two-way traffic Monday through Friday to install new Pleasant Home Water District water lines.
-
Altman Road/Lusted Road intersection: Flagged two-way traffic Monday through Friday to install new Pleasant Home Water District water lines.
-
Dodge Park Boulevard (west of Cottrell Road) through August 31: Flagged two-way traffic Monday through Saturday to clear, grub, and prepare for pipeline installation in the public right-of-way on the south side of the road.
-
Dodge Park Boulevard (east of Cottrell Road) through August 31: Flagged two-way traffic Monday through Saturday to clear, grub, and prepare for pipeline installation in the public right-of-way on the south side of the road.
-
Lusted Road near the county line: Flagged two-way traffic 24/7 Monday through Friday.
What to expect:
- Flaggers and temporary traffic controls to direct traffic
- Surveyors working in the public right-of-way
- Local and emergency access will be maintained
Proceed with Caution
-
Cottrell Road south of Dodge Park:We are aware of the uneven road surface (a dip) on Cottrell Road between Dodge Park Boulevard and Bluff Road. We're working with Multnomah County to repave the road soon. Signs with lights have been added to alert drivers in the interim. Please use caution when driving through this section of the road.
Other work happening the week of August 4
Staff will be at the project work sites during shift hours to perform various tasks. Work hours will be between 7 a.m. and 6 p.m., Monday through Saturday.
Filtration facility site activities include:
-
Off-hauling clean soils to permitted locations using approved haul routes
-
Delivering equipment and materials to the site
-
Remobilizing construction equipment
- Installing concrete formwork, piping, and utilities on site
- Ongoing stormwater management and erosion control
- As needed street sweeping
- Ongoing 24/7 site security
Finished water pipeline site activities include:
- Survey work along Altman Road between Pipeline Road and Oxbow Drive
- Remobilizing construction equipment and installing traffic control barriers around work zones on Dodge Park Boulevard
- Clearing, grubbing, and stump removal from public right-of-way along south side of Dodge Park Boulevard
- Ongoing stormwater management and erosion control
Finished water intertie site activities include:
- Remobilizing construction equipment
- Ongoing stormwater management and erosion control
Raw water tunnel/pipeline site activities include:
- Remobilizing construction equipment
- Ongoing stormwater management and erosion control
Bull Run Filtration: neighbor update meeting
The Water Bureau will host an online community meeting to update neighbors on progress for Bull Run Filtration Project construction.
Date: Wednesday, August 13, 2025
Time: 6 p.m.
Where: Zoom meeting (register to attend)
Can't make this neighbor update meeting? Join us at the next in-person Coffee with the Contractor on September 11.
|
|
Get construction text alerts
Sign up to receive text notifications about temporary lane closures and other construction traffic information related to the Bull Run Filtration project.
|
|
|
The Bull Run Filtration Project will remove Cryptosporidium and other contaminants from the Bull Run water supply, producing cleaner, safer water for the one million people who use our water now and for future generations. The project is required by the federal Safe Drinking Water Act and must be in operation by September 30, 2027, through a bilateral compliance agreement with the Oregon Health Authority.
To learn more, visit portland.gov/water/filtration.
|
|
|
Know someone who would be interested in updates about the Bull Run Treatment Projects? Please share the news!

The City of Portland is committed to providing meaningful access. To request translation, interpretation, modifications, accommodations, or other auxiliary aids or services, or to file a complaint of discrimination, contact 503-823-4000 (311), Relay Service & TTY: 711
Traducción e Interpretación | Biên Dịch và Thông Dịch | अनुवादन तथा व्याख्या 口笔译服务 | Устный и письменный перевод | Turjumaad iyo Fasiraad Письмовий і усний переклад | Traducere și interpretariat | Chiaku me Awewen Kapas Translation and Interpretation: 503-823-4000 (311), Relay: 711
This email was sent from an unmonitored inbox. Please do not reply. Instead, contact us at bullrunprojects@portlandoregon.gov.
|
|
|
|