 We are working to address road condition concerns on Cottrell Road and have temporarily halted use of Cottrell Road between Lusted Road and Dodge Park Boulevard by haul traffic. We are planning to resurface Cottrell Road early this year, and in the meantime, crews are repairing the potholes as a temporary solution.
We also understand Multnomah County will be doing pothole repairs on Dodge Park Boulevard between Pleasant Home Road and Orient Drive in the coming weeks.
Starting in late January or February, crews will mobilize for pipeline construction on Dodge Park Boulevard. Throughout this year, we will be installing a new large-diameter pipeline in the south side of the Dodge Park Boulevard right-of-way, with work expected to start near the Cottrell Road intersection and move west. After the pipeline construction is complete, the work area and road surface will be restored.
Temporary traffic controls include:
-
Lusted Road (between Hosner Road and Altman Road): Flagged one-way westbound traffic while crews install water lines on the south side of Lusted Road between the intertie site and Altman Road intersection. Eastbound traffic will be detoured to Oxbow Drive or Dodge Park Boulevard--school buses and farm traffic will be flagged through west to east during shift hours as needed.
-
Lusted Road (near county line): Single-lane closure with flagged two-way traffic to allow for temporary widening within the Lusted Road right-of-way.
What to expect:
- Signage and temporary traffic controls to direct traffic
- Local and emergency access will be maintained
- Flaggers will prioritize school buses and farm traffic
- Normal traffic flow will resume outside shift hours
Note: Temporary closure of the Lusted Road/Altman Road intersection during shift hours is anticipated February 3-7. Temporary closure of part of Pipeline Road near the intersection with Altman Road is anticipated in February or March for one to two weeks. Additional information will be shared as available.
Construction activity for week beginning January 13, 2025
Construction work hours will be between 7 a.m. and 6 p.m., Monday through Saturday. Deliveries and work to prepare or secure the sites for the day may occur outside of these hours.
Our goal is not to have any appreciable sediment leave the project site. If sediment is inadvertently tracked off-site, we will continue to use a street sweeper as necessary to clean the haul routes within the project study area.
Work at the filtration facility site includes:
- Off-hauling both clean and contaminated soils to permitted disposal locations using approved haul routes (Mon-Sat)
- Delivering equipment and materials, including large piping and materials for backfilling
- Installing sheet piles to create in-ground retaining walls (vibration and metal noise through mid-February)
- Ramping up concrete work and beginning to pour pipe encasements, deep sumps, and building slabs
- Ongoing installation of piping and some excavation and grading for various facilities
- Installing guide wall for pipeline shaft in southeast corner of site
What to expect:
- 24-hour site security
- Increased traffic near the site
- Construction noise and vibration near the site
Work at the finished water pipeline site on Carpenter Lane includes:
- Excavating pipeline shaft and installing caisson
What to expect:
- Increased traffic near the site
- Construction noise and vibration near the site
Work at the raw water pipeline/tunnel site on Lusted Road near the Clackamas/Multnomah county line includes:
- Delivering equipment and materials to the site
- Excavating pipeline portal and installing soldier piles
What to expect:
- Increased traffic near the site
- Flaggers for traffic safety when vehicles are entering and exiting the site
- Construction noise and vibration near the site
Work at the finished water intertie site on Lusted Road includes:
- Installing temporary fencing
- Moving stockpiled soils
What to expect:
- Increased traffic near the site
- Flaggers for traffic safety when vehicles are entering and exiting the site
- Construction noise and vibration near the site
Work schedules are subject to change depending on weather and other field conditions. For the latest information about current and upcoming construction activities, visit portland.gov/FiltrationConstruction.
Bull Run Filtration: Neighbor Update Meeting (Jan 2025)
At the January 9 meeting, community members heard an update on pipeline and facility construction for the Bull Run Filtration projects. The meeting included discussion about use and maintenance of project construction haul routes, upcoming traffic restrictions in the project area, and planned construction methods for the pipeline tunnel excavation.
Visit the January 2025 Neighbor Update Meeting webpage to see the meeting presentation and recording.
Bull Run Filtration: Coffee with the Contractor
The Water Bureau will host an informal drop-in session where project neighbors can talk with representatives of the facility and pipeline construction teams, ask questions, and hear about recent progress and upcoming work. There is no presentation, so stop in anytime between 9 and 10 a.m.
Date: Thursday, February 13, 2025
Time: 9-10 am (drop in)
Where: Sandy Community/Senior Center ‘Dining Room’ 38348 Pioneer Boulevard, Sandy, Oregon 97055
Can't make the meeting this time? Join us for the in-person Coffee with the Contractor on March 13.
|