 We hope everyone is enjoying the holidays! We expect limited work activity early in the week. No work is planned January 1.
After New Year's Day, temporary traffic controls for work on Lusted Road east of Altman Road and on Lusted Road near the county line will resume.
Single-lane traffic controls include:
-
Lusted Road (between Hosner Road and Altman Road): Flagged one-way westbound traffic while crews install water lines on the south side of Lusted Road between the intertie site and Altman Road intersection. Eastbound traffic will be detoured to Oxbow Drive or Dodge Park Boulevard--school buses and farm traffic will be flagged through west to east during shift hours as needed.
-
Lusted Road (near county line): Single-lane closure with flagged two-way traffic to allow for temporary widening within the Lusted Road right-of-way.
What to expect:
- Signage and temporary traffic controls to direct traffic
- Local and emergency access will be maintained
- Flaggers will prioritize school buses and farm traffic
- Normal traffic flow will resume outside shift hours
Note: Temporary full closure of the Altman Road/Lusted Road intersection is expected between January 15 and January 24. We also anticipate temporary closures of Pipeline Road at the intersection with Altman Road and of Oxbow Drive near the intersection with Altman Road in February.
Additional information will be shared as available.
Construction activity for week beginning December 30, 2024
Construction work hours will be between 7 a.m. and 6 p.m., Monday through Saturday. No work is planned January 1. Deliveries and work to prepare or secure the sites for the day may occur outside of these hours.
Work at the filtration facility site includes:
- Off-hauling both clean and contaminated soils to permitted disposal locations using approved haul routes (Mon-Sat)
- Delivering equipment and materials, including large piping and materials for backfilling
- Installing sheet piles to create in-ground retaining walls (vibration and metal noise)
- Ramping up concrete work and beginning to pour pipe encasements, deep sumps, and building slabs
- Ongoing installation of piping and some excavation and grading for various facilities
- Excavating pipeline shaft in southeast corner of site
What to expect:
- 24-hour site security
- Increased traffic near the site
- Construction noise and vibration near the site
- Street sweeper operating on Carpenter Lane
Work at the finished water pipeline site on Carpenter Lane includes:
- Setting up micro tunnel boring machine
What to expect:
- Increased traffic near the site
- Construction noise and vibration near the site
Work at the raw water pipeline/tunnel site on Lusted Road near the Clackamas/Multnomah county line includes:
- Delivering equipment and materials to the site
- Excavating pipeline portal and installing soldier piles
What to expect:
- Increased traffic near the site
- Flaggers for traffic safety when vehicles are entering and exiting the site
- Construction noise and vibration near the site
- Street sweeper operating on Lusted Road
Work schedules are subject to change depending on weather and other field conditions. For the latest information about current and upcoming construction activities, visit portland.gov/FiltrationConstruction.
Bull Run Filtration: Neighbor Update Meeting (January 2025)
The Water Bureau will host an online community meeting to update neighbors on progress and upcoming construction work for the Bull Run Filtration projects.
Date: Thursday, January 9, 2025
Time: 6 pm
Where: Zoom (register here)
Can't make the meeting this time? Join us for the in-person Coffee with the Contractor on February 13.
|