Early in the week, there will be temporary traffic controls where work is happening in the Altman Road right-of-way between Oxbow Drive and Lusted Road.
No work is planned Thursday or Friday--we wish everyone a happy Thanksgiving!
Following the holiday, crews will be working on Lusted Road east of the Altman Road intersection to begin installing new Pleasant Home Water District water lines.
Single-lane closures and traffic controls include:
-
Altman Rd (between Oxbow Drive and Lusted Road, including Pipeline Road intersection and Lusted Road intersection): There will be traffic controls with flagged two-way traffic in the open lane while crews pothole to confirm the location of existing underground utilities.
What to expect:
- Signage and temporary traffic controls to direct traffic
- Local and emergency access will be maintained
Note: A temporary full closure of the Altman Road/Lusted Road intersection is planned between December 16 and January 3. Detours for through traffic will be signed and the intersection will be open to regular traffic outside of shift hours. Additional information will be shared as available.
Construction activity for week beginning November 25, 2024
Construction work hours will be between 7 a.m. and 6 p.m., Monday through Wednesday. No work is planned November 28-29. Deliveries and work to prepare or secure the sites for the day may occur outside of these hours.
Work at the filtration facility site includes:
What to expect:
- 24-hour site security
- Increased traffic near the site
- Construction noise and vibration near the site
- Street sweeper operating on Carpenter Lane
Work at the finished water pipeline site on Carpenter Lane includes:
- Installing caisson launch shaft for pipeline
What to expect:
- Increased traffic near the site
- Construction noise and vibration near the site
Work at the raw water pipeline/tunnel site on Lusted Road near the Clackamas/Multnomah county line includes:
- Mobilizing equipment to site
- Installing fencing and temporary utilities
- Assembling temporary construction office trailers and storage
- Preparing for tunnel construction, including installing soldier piles
What to expect:
- Increased traffic near the site
- Flaggers for traffic safety when vehicles are entering and exiting the site
- Construction noise and vibration near the site
- Street sweeper operating on Lusted Road
Work at the finished water intertie site and in the City-owned easement east of Altman Road between Lusted Road and Dodge Park Boulevard includes:
- Mobilizing equipment to site
- Installing fencing and temporary utilities
- Preparing for access road construction
What to expect:
- Increased traffic near the site
- Flaggers for traffic safety when vehicles are entering and exiting the site
- Construction noise and vibration near the site
- Street sweeper operating on Lusted Road
Work schedules are subject to change depending on weather and other field conditions. For the latest information about current and upcoming construction activities, visit portland.gov/FiltrationConstruction.
Bull Run Filtration: Coffee with the Contractor
The Water Bureau will host an informal drop-in session where Bull Run Filtration Project neighbors can chat with representatives of the facility and pipeline construction teams, ask questions, and hear about recent progress and upcoming work. There is no presentation, so stop in anytime between 9-10:30 am.
Date: Thursday, December 12, 2024
Time: 9-10:30 am
Where: Multnomah Grange #71 30639 SE Bluff Road, Gresham
Can't make the meeting this time? Join us for the virtual Neighbor Update Meeting on January 9.
|