Expect ongoing single-lane closures on Altman Road as crews pave the recently widened east side of Altman Road, between Pipeline Road and Lusted Road. This will help with traffic management during upcoming pipeline construction, including installation of new Pleasant Home Water District water mains expected to start mid-November on Lusted Road east of the Altman Road intersection.
Work to clear vegetation on the south side of Dodge Park Boulevard was completed this week ahead of schedule. This recent work will help prepare a work area in the public right-of-way for the Dodge Park Boulevard pipeline construction expected to begin in 2025.
Contractors are continuing to move stockpiled clean soils off the facility site using the allowed haul routes for project construction truck traffic. This truck traffic will be ongoing until the stockpiled clean soils are removed from the site.
Single-lane closures and traffic controls include:
- Altman Road - between Pipeline Road and Lusted Road
- Carpenter Lane - east of Cottrell Road
What to expect:
- Signage and flaggers will direct traffic
- Local and emergency access will be maintained
Note: A temporary full closure of the Altman Rd/Lusted Rd intersection is planned November 19-27. Additional information will be shared as available.
Construction activity for week beginning October 28, 2024
Construction work hours will be between 7 a.m. and 6 p.m., Monday through Saturday. Deliveries and work to prepare or secure the sites for the day may occur outside of these hours.
Work at and near the filtration facility site includes:
- Off-hauling clean soils (currently Mon-Fri)
- Some patch paving on Carpenter Lane (east of Cottrell Road)
- Delivering equipment and materials to the facility site, including large-diameter pipeline and backfill materials
- Working on subgrade to final depth and preparing for underdrain piping
- Excavating and grading for crane pads and non-process buildings
- Installing sheet piles to create in-ground retaining walls on site (vibration and metal noise through November)
- Installing temporary water and electric utilities on site
- Operating water trucks onsite for dust control
- Stabilizing soils, including use of tackifier, to keep soil and dust from leaving stockpiles
What to expect:
- 24-hour site security
- Increased traffic near the site
- Construction noise and vibration near the site
- Street sweeper operating on Carpenter Lane
- Contractor will suspend activities to allow emergency access and local residents access to their property
Work at the raw water pipeline/tunnel site on Lusted Road near the Clackamas/Multnomah county line includes:
- Mobilizing equipment to site
-
Installing security fencing
-
Building work site access road
-
Rocking construction laydown yards
What to expect:
- Increased traffic near the site
- Flaggers for traffic safety when vehicles are entering and exiting the site
- Construction noise and vibration near the site
- Street sweeper operating on Lusted Road
Work at the finished water intertie site and in the City-owned easement east of Altman Road between Lusted Road and Dodge Park Boulevard includes:
- Mobilizing equipment to site
-
Clearing, grubbing, and tree removal
-
Installing site perimeter fencing
-
Building work site access road
What to expect:
- Increased traffic near the site
- Flaggers for traffic safety when vehicles are entering and exiting the site
- Construction noise and vibration near the site
- Street sweeper operating on Lusted Road
Work in the public right-of-way on Altman Road includes:
- Completing paving of widened road on the east side of Altman Road between Pipeline Road and Lusted Road
What to expect:
- Single-lane closures with traffic controls and flaggers to direct traffic
Find additional information about current and upcoming construction activities at portland.gov/FiltrationConstruction.
Bull Run Filtration: Coffee with the Contractor
The Water Bureau will host an informal drop-in session where Bull Run Filtration Project neighbors can chat with representatives of the facility and pipeline construction teams, ask questions, and hear about recent progress and upcoming work. There is no presentation, so stop in anytime between 9-10:30am.
Date: Thursday, November 14, 2024
Time: 9-10:30am
Where: Multnomah Grange #71, 30639 SE Bluff Rd, Gresham, OR 97080
Can't make the meeting this time? Join us at the next Coffee with the Contractor on December 12.
|