Crews are working to widen the east side of Altman Road, between Pipeline Road and Lusted Road, to help with traffic management during upcoming pipeline construction. A new Pleasant Home Water District water line will be installed in this stretch of Altman later this year.
Improvements to the facility site access on Cottrell Road between Carpenter Lane and Dodge Park Boulevard are nearly finished. The "top lift" paving of this part of Cottrell Road is planned for Saturday October 12 and Monday October 14, followed by shoulder restoration work.
For several months, contractors have been excavating and stockpiling clean soils at the facility site. With the "fix-it-first" road improvements wrapped up, contractors are now beginning to move those clean soils off site using the allowed haul routes for project. This truck traffic will be ongoing for the foreseeable future until the stockpiled clean soils are removed from the site.
Single-lane closures and traffic controls include:
- Altman Road - between Pipeline Road and Lusted Road
- Carpenter Lane - east of Cottrell Road
- Cottrell Road - between Dodge Park Boulevard and Carpenter Lane (including Saturday Oct. 12)
What to expect:
- Signage and flaggers will direct traffic
- Local and emergency access will be maintained
Note: temporary full closures are planned for the Altman Rd/Lusted Rd intersection and for Lusted Rd near the county line in November and December. Additional information will be shared as available.
Construction activity for week beginning October 14, 2024
Construction work hours will be between 7 a.m. and 6 p.m., Monday through Saturday. Deliveries and work to prepare or secure the sites for the day may occur outside of these hours.
Work at and near the filtration facility site includes:
- Off-hauling clean soils from the site
- Completing paving improvements and working on overhead utilities on Cottrell Road (between Carpenter Lane and Dodge Park Boulevard)
- Working on overhead utilities and removing old utility poles on Carpenter Lane (east of Cottrell Road)
- Delivering equipment and materials to the site, including large crawler crane and temporary offices
- Installing sheet piles to create an in-ground retaining wall at the site (vibration and metal noise through October)
- Installing temporary water and electric utilities at the site
- Working on subgrade to final depth and preparing for underdrain piping on site
- Excavating and grading for crane pads and non-process buildings
- Operating water trucks onsite for dust control
- Stabilizing soils, including use of tackifier, to keep soil and dust from leaving stockpiles
What to expect:
- 24-hour site security
- Increased traffic near the site
- Signage and flaggers directing traffic
- Street sweeper operating on Carpenter Lane
- Construction noise and vibration near the site
- Contractor will suspend activities to allow local residents access to their property
Work at the raw water pipeline/tunnel site on Lusted Road near the Clackamas/Multnomah county line includes:
- Mobilizing equipment to site
-
Installing final security fence and gates
-
Building work site access road
-
Rocking construction laydown yards
What to expect:
- Increased traffic near the site
- Flaggers for traffic safety when vehicles are entering and exiting the site
- Construction noise and vibration near the site
- Street sweeper operating on Lusted Road
Work at the finished water intertie site and in the City-owned easement east of Altman Road between Lusted Road and Dodge Park Boulevard includes:
- Mobilizing equipment to site
-
Clearing, grubbing, and tree removal
-
Installing site perimeter fencing
-
Building work site access road
What to expect:
- Increased traffic near the site
- Flaggers for traffic safety when vehicles are entering and exiting the site
- Construction noise and vibration near the site
- Street sweeper operating on Lusted Road
Work in the public right-of-way on Lusted Road and on Altman Road, between Pipeline Road and Lusted Road, includes:
- Road widening on the east side of Altman Road
- PGE working clearance along Lusted Road
What to expect:
- Single-lane closures with traffic controls and flaggers to direct traffic
Find additional information about current and upcoming construction activities at portland.gov/FiltrationConstruction.
Bull Run Filtration: Neighbor Update Meeting
At the October 10, 2024 meeting, community members heard an update on pipeline and facility construction for the Bull Run Filtration Project. Visit the October 2024 Neighbor Update Meeting webpage to see the meeting presentation and recording.
Bull Run Filtration: Coffee with the Contractor
The Water Bureau will host an informal drop-in session where Bull Run Filtration Project neighbors can chat with representatives of the facility and pipeline construction teams, ask questions, and hear about recent progress and upcoming work. There is no presentation, so stop in anytime between 9-10:30am.
Date: Thursday, November 14, 2024
Time: 9-10:30am
Where: updated location coming soon
Can't make the meeting this time? Join us at the next Coffee with the Contractor on December 12.
|