ODOT Project manager Tony Snyder (pictured above, right) has issued a notice to proceed for general contractor David Evans & Associates and architect Nathan Good. This is for the initial work required in order to find out what is feasible for an eventual design... Read more »

=============
Congressman Peter DeFazio and the new train

Oregon's new trains welcomed in July

A ribbon-cutting ceremony featuring elected officials, train fans and even representatives from the Spanish manufacturer, Talgo, joined the festivities in late July in Eugene... Read more »

=============

IN THIS ISSUE

=============

Here is an estimated timeline for restoring the historic Salem Railroad Baggage Depot and updating the surrounding area:

  • Fall 2013: conduct preliminary work
  • Early 2014: issue request-for-proposals; get bids
  • Summer 2014: begin construction

 We'll know more about this after the initial work is completed by the current contractors.

 

Salem RR Baggage Depot

Advisory group tours the area

=============

In July a group gathered to take a tour of the historic Salem Railroad Baggage Depot. The team will serve as "technical advisors" for the project. For more information, contact Jean Palmateer at ODOT, jean.m.palmateer@odot.state.or.us. 


Advisory team
=============